    "tag": [
        "compiled"
    ],
    "id": "ocds-b5fd17-14189b2f-a65e-4cbd-84d2-05676a0751ca-2026-03-19T14:38:48Z",
    "date": "2026-03-19T14:38:48Z",
    "ocid": "ocds-b5fd17-14189b2f-a65e-4cbd-84d2-05676a0751ca",
    "language": "en",
    "initiationType": "tender",
    "planning": {
        "documents": [
            {
                "id": "1",
                "documentType": "plannedProcurementNotice",
                "description": "Future opportunity notice on Contracts Finder",
                "url": "https://www.contractsfinder.service.gov.uk/Notice/550e2499-b437-4f0b-8773-b1f3cf975927",
                "datePublished": "2026-03-19T14:38:48Z",
                "format": "text/html",
                "language": "en"
            }
        ]
    },
    "tender": {
        "id": "tender_524385/1561308",
        "title": "SUPPLY CHAIN NOTICE - Central Substation RIBA4 & Build",
        "description": "The overarching requirement of the project is to develop the RIBA Stage 3 Design into a complete RIBA Stage 4 Technical Design and subsequently build and commission the new Central Substation building (through RIBA Stage 5 and 6). This project is split into two principal Phases as outlined below - a Design Phase (1) and a Build Phase (2), each with their own corresponding Work Packages. In summary, this Project includes the following work packages: Project Phase 1 (Design) includes the following work packages: - WP 1: Survey and assessment work to facilitate the RIBA 4 design. - WP 2: RIBA 4 Technical Design incl. all temporary works designs. - WP 3: Undertake earthing design for Central Substation. Project Phase 2 (Build) includes the following work package: - WP 4: RIBA 5 and 6: Construct, Commission and Handover the works as designed in Phase 1. Installation of HV/LV Electrical switch panels and associated cabling shall not form part of this work, and will follow as a separate project once WP 4 is complete. Those that meet the criteria of this initial phase will be invited to participate in a final competition. Deadlines for expressions of interest are the 27th March. Any expressions received after this date will not be accepted.",
        "status": "planned",
        "classification": {
            "scheme": "CPV",
            "id": "45232220",
            "description": "Substation construction work"
        },
        "items": [
            {
                "id": "1",
                "deliveryAddresses": [
                    {
                        "postalCode": "PO1 3LS"
                    },
                    {
                        "region": "South East",
                        "countryName": "United Kingdom"
                    }
                ]
            }
        ],
        "value": {
            "amount": 1300000,
            "currency": "GBP"
        },
        "communication": {
            "futureNoticeDate": "2026-02-25T23:59:59Z"
        },
        "contractPeriod": {
            "startDate": "2026-07-01T00:00:00+01:00",
            "endDate": "2027-07-01T23:59:59+01:00"
        },
        "suitability": {
            "sme": true,
            "vcse": false
        }
    },
    "parties": [
        {
            "id": "GB-CFS-238029",
            "name": "Ministry of Defence",
            "identifier": {
                "legalName": "Ministry of Defence"
            },
            "address": {
                "streetAddress": "Victory Building, Portsmouth Naval Base",
                "locality": "Portsmouth",
                "postalCode": "PO1 3LS",
                "countryName": "England"
            },
            "contactPoint": {
                "name": "Abi Millyard",
                "email": "scsystems@kbsmaritime.com"
            },
            "roles": [
                "buyer"
            ]
        }
    ],
    "buyer": {
        "id": "GB-CFS-238029",
        "name": "Ministry of Defence"
    }
}