title: "Building Decarbonisation Projects at Williamson Park, The Storey and City Lab"
ocid: "ocds-h6vhtk-04e7c4"
canonical_url: "https://d3tenders.com/contract/?ocid=ocds-h6vhtk-04e7c4"
markdown_url: "https://d3tenders.com/contract/ocds-h6vhtk-04e7c4.md"
json_url: "https://d3tenders.com/contract/ocds-h6vhtk-04e7c4.json"
source: "Find A Tender Service"
current_stage: "Award"
buyer: "LANCASTER CITY COUNCIL"
published: "2025-07-07"
---

# Building Decarbonisation Projects at Williamson Park, The Storey and City Lab

Buyer: LANCASTER CITY COUNCIL  
Current stage: Award  
OCID: ocds-h6vhtk-04e7c4

[View canonical contract page](https://d3tenders.com/contract/?ocid=ocds-h6vhtk-04e7c4)  
[Download OCDS JSON](https://d3tenders.com/contract/ocds-h6vhtk-04e7c4.json)

## Summary

The procurement process for the "Building Decarbonisation Projects at Williamson Park, The Storey and City Lab" is overseen by Lancaster City Council, a regional authority in the United Kingdom. The contract, concluded under an open procurement procedure, encompasses construction work aimed at reducing carbon emissions. The process is currently in the Award stage, with Alternative Heat Ltd being the appointed contractor. Pre-construction services have commenced, focusing on the technical design phase, and the project must reach practical completion by January 2026, with an initial target of December 2025. The works are partially funded through the Public Sector Decarbonisation Scheme, underscoring the project's priority in sustainable development.

This tender offers significant opportunities for businesses specialising in construction and energy efficiency solutions, particularly those with expertise in buildability input, detailed cost estimation, and risk management during pre-construction phases. Larger firms like Alternative Heat Ltd, which has been awarded the contract, demonstrate the type of agency likely to compete effectively, especially considering the project's scale and the quality, social value, and price criteria defined. Businesses capable of innovating in sustainable energy solutions and with robust technical support can leverage this tender to enhance their market presence and credibility in the public sector. The project's focus on decarbonisation aligns well with current trends in environmentally responsible construction, making it an attractive proposition for businesses aiming to expand in this sector.

## Notice

Phase 1 - Pre-Construction Services (RIBA Stage 4) The initial appointment will be for the pre-construction services, which encompass the completion of RIBA Stage 4 (Technical Design). The contractor will be responsible for providing detailed input on the buildability of the design, collaborating with the design team to ensure constructability, and contributing to cost estimation, planning, and risk identification during this phase. Key Responsibilities for RIBA Stage 4: * Provide buildability input to ensure the design can be practically constructed and meets the required performance specifications. * Assist with detailed cost estimation, including providing open book pricing. * Contribute to risk management by identifying potential risks and proposing mitigation strategies. * Review and validate the design to confirm that it aligns with project requirements and is feasible for construction. Page 4 to 10 Phase 2 - Construction Works (RIBA Stage 5 and 6) The ITT also includes the potential for the appointed Contractor to undertake the construction works, which cover RIBA Stage 5 (Construction) and RIBA Stage 6 (Handover and Close Out). However, the appointment for these stages is not guaranteed at this point. Upon the completion of RIBA Stage 4, a formal review will be conducted to assess the Contractor's performance and the project's requirements. The Council reserves the right to proceed with the contractor for the construction works, subject to satisfactory performance during RIBA Stage 4, confirmation of costs, and overall project alignment. A break clause will be in place, allowing the Council to either proceed with the appointed Contractor or re-tender for the construction works. The Council retains Intellectual Property over full design work specific to the sites of this project for use with another contractor if required. Key Points for RIBA Stage 5 and 6: * The ITT outlines the requirements for both pre-construction services and potential construction works, but the contractor is only guaranteed the work for RIBA Stage 4. * Following the completion of RIBA Stage 4, the Council will review whether to appoint the contractor for RIBA Stage 5 and 6 based on performance, costs, and other considerations. The main contract is subject to obtaining all necessary planning consents. The responsibility for securing these consents will primarily rest with the Council. However, the appointed contractor will be expected to provide technical support and relevant information as required during the planning process. The contractor must be aware that no construction works, particularly any equipment ordering or significant on-site activities, can commence until all planning permissions are secured. The timeline for the project may be extended if planning approvals are delayed. Coordination with external parties, may also impact the timing of planning approvals and should be factored into the project delivery plan. The project is partially funded through the Public Sector Decarbonisation Scheme (PSDS), and the key funding condition is that the project must be fully delivered, reach Practical Completion (PC), and be signed off by the end of January 2026. This is the final deadline for the project, and all works must be completed, tested, commissioned, and handed over before this date to ensure compliance with funding requirements. While an initial target of December 2025 has been identified for completion, this is flexible to avoid unnecessary risk. The Council prefers to extend the timeline if required to ensure quality and performance, rather than rush delivery.

### Lot Information

Lot 1

Phase 1 - Pre-Construction Services (RIBA Stage 4) The initial appointment will be for the pre-construction services, which encompass the completion of RIBA Stage 4 (Technical Design). The contractor will be responsible for providing detailed input on the buildability of the design, collaborating with the design team to ensure constructability, and contributing to cost estimation, planning, and risk identification during this phase. Key Responsibilities for RIBA Stage 4: * Provide buildability input to ensure the design can be practically constructed and meets the required performance specifications. * Assist with detailed cost estimation, including providing open book pricing. * Contribute to risk management by identifying potential risks and proposing mitigation strategies. * Review and validate the design to confirm that it aligns with project requirements and is feasible for construction. Page 4 to 10 Phase 2 - Construction Works (RIBA Stage 5 and 6) The ITT also includes the potential for the appointed Contractor to undertake the construction works, which cover RIBA Stage 5 (Construction) and RIBA Stage 6 (Handover and Close Out). However, the appointment for these stages is not guaranteed at this point. Upon the completion of RIBA Stage 4, a formal review will be conducted to assess the Contractor's performance and the project's requirements. The Council reserves the right to proceed with the contractor for the construction works, subject to satisfactory performance during RIBA Stage 4, confirmation of costs, and overall project alignment. A break clause will be in place, allowing the Council to either proceed with the appointed Contractor or re-tender for the construction works. The Council retains Intellectual Property over full design work specific to the sites of this project for use with another contractor if required. Key Points for RIBA Stage 5 and 6: * The ITT outlines the requirements for both pre-construction services and potential construction works, but the contractor is only guaranteed the work for RIBA Stage 4. * Following the completion of RIBA Stage 4, the Council will review whether to appoint the contractor for RIBA Stage 5 and 6 based on performance, costs, and other considerations. The main contract is subject to obtaining all necessary planning consents. The responsibility for securing these consents will primarily rest with the Council. However, the appointed contractor will be expected to provide technical support and relevant information as required during the planning process. The contractor must be aware that no construction works, particularly any equipment ordering or significant on-site activities, can commence until all planning permissions are secured. The timeline for the project may be extended if planning approvals are delayed. Coordination with external parties, may also impact the timing of planning approvals and should be factored into the project delivery plan. The project is partially funded through the Public Sector Decarbonisation Scheme (PSDS), and the key funding condition is that the project must be fully delivered, reach Practical Completion (PC), and be signed off by the end of January 2026. This is the final deadline for the project, and all works must be completed, tested, commissioned, and handed over before this date to ensure compliance with funding requirements. While an initial target of December 2025 has been identified for completion, this is flexible to avoid unnecessary risk. The Council prefers to extend the timeline if required to ensure quality and performance, rather than rush delivery.

## Key Details

| Field | Value |
| --- | --- |
| Publication source | Find A Tender Service |
| Latest notice | https://www.find-tender.service.gov.uk/Notice/037694-2025 |
| Notice type | Tender Notice |
| Procurement type | Standard |
| Procurement category | Works |
| Procurement method | Open |
| Procurement method details | Open procedure |
| Tender suitability | Not specified |
| Awardee scale | Large |
| All stages | Tender, Award |

## Dates

| Field | Value |
| --- | --- |
| Publication date | 7 Jul 2025 |
| Submission deadline | 13 Mar 2025 |
| Future notice date | Not specified |
| Award date | 6 Jul 2025 |
| Contract period | Not specified |
| Recurrence | Not specified |

## Values

| Field | Value |
| --- | --- |
| Tender value | £3,200,000 |
| Lots value | £3,200,000 |
| Awards value | Not specified |
| Contracts value | £2,937,317 |

## Status

| Field | Value |
| --- | --- |
| Tender status | Complete |
| Lots status | Cancelled |
| Awards status | Active |
| Contracts status | Active |

## Buyer

| Field | Value |
| --- | --- |
| Main buyer | LANCASTER CITY COUNCIL |
| Locality | LANCASTER |
| Post town | Lancaster |
| Postcode | LA1 1PJ |
| Country | England |
| ITL 1 | TLD North West (England) |
| ITL 2 | TLD4 Lancashire |
| ITL 3 | TLD44 Lancaster and Wyre |
| Local authority | Lancaster |
| Electoral ward | Castle |
| Westminster constituency | Lancaster and Wyre |
| Delivery location | Not specified |

## Supplier

| Field | Value |
| --- | --- |
| Number of suppliers | 1 |
| Supplier names | ALTERNATIVE HEAT |

## CPV Codes

### Divisions

- 45 - Construction work

### Codes

- 45000000 - Construction work

## Release History

- 7 Jul 2025 at 10:30 - Award - Award Notice - https://www.find-tender.service.gov.uk/Notice/037694-2025
- 25 Feb 2025 at 12:36 - Tender - Tender Notice - https://www.find-tender.service.gov.uk/Notice/007149-2025

## Notice URLs

- http://www.lancaster.gov.uk/
- https://procontract.due-north.com/Advert/Index?advertId=43ce19cf-dda5-ef11-8132-005056b64545

## Provenance

This Markdown file is an alternate public rendering of the D3 Tenders contract record. The canonical page is https://d3tenders.com/contract/?ocid=ocds-h6vhtk-04e7c4. The underlying structured data is available as OCDS JSON at https://d3tenders.com/contract/ocds-h6vhtk-04e7c4.json.