Homes England commissioned property valuation and development advisory services for the Worcestershire Parkway development. The work covers a methodology for valuing strategic infrastructure and non-residential land across large consortium developments, including education, healthcare, open space, green infrastructure, community facilities, emergency services, transport, rail and utilities. The consultant must also assess the value attributable to Network Rail land, assets, rights or interventions in the Wychavon Town shared-value discussions, review relevant costs and offsets, and provide negotiation advice. The work includes reviewing project information and existing models, developing guidance and worked examples, testing assumptions, and setting out an auditable basis for the assessment. The buyer is Homes England. The services are classified as real estate services and relate to Worcestershire Parkway and Wychavon Town.

The procurement is complete and the contract has been awarded to Montagu Evans LLP under a selective below-threshold route, as an award under an existing framework. The contract was signed on 5 October 2026 and runs from 6 October 2026 to 19 August 2027. Its value is £60,000 excluding VAT (£72,000 including VAT). The competition was identified as competitive. One lot is recorded as complete. The published procurement data does not state an evaluation formula or award criteria, so the basis on which competing offers were assessed cannot be described.

This award shows demand from Homes England for specialist valuation and development advice on major consortium schemes, strategic infrastructure and non-residential land. A credible competitor for a future requirement would need senior valuation expertise and the ability to assess existing-use, market, development and residual values, land-value uplift and shared value. Relevant capability includes advising on infrastructure costs, land assembly, obligations, phasing, risk and value attribution; working with confidential information across multiple developers and landowners; and applying sound governance and assurance. The work also calls for clear, evidence-led reporting, sensitivity testing, worked examples and an audit trail, alongside the ability to assess rail assets and operational dependencies and support commercial negotiations with Network Rail. Suppliers experienced in public-sector development and viability modelling would be well placed.

How relevant is this notice?

Notice Information

Notice Title

Homes England - Property, Financial and Development Services Framework- Worcestershire Parkway - lot 1

Notice Description

Service 1 - Strategic Infrastructure and Non-Residential Land Valuation Framework Workstream 1 - Inception, Information Review and Project Management * Attend one inception meeting of up to two hours within one week of appointment. * Review the project information made available by Homes England, including masterplans, planning and development assumptions, infrastructure and transport strategies, programme information, consortium arrangements, land ownership information, relevant legal agreements, cost estimates, viability and financial modelling and Network Rail correspondence. * Prepare an Information Requirements Schedule identifying information required, its purpose, owner, priority and any implications if unavailable. * Confirm the proposed methodology, programme, deliverables, review process and reporting arrangements in an inception note. * Maintain an issues, assumptions and decisions log throughout the commission. * Attend up to two progress meetings of up to one hour each in addition to the specific meetings identified below. Workstream 2 - Valuation Principles and Methodology * Develop a valuation methodology for strategic infrastructure and non-residential land uses on large consortium developments. * Consider appropriate approaches to existing use value, market value, development value, residual value, land value uplift, opportunity cost and value sharing. * Explain when each approach should be used, the evidence required, key assumptions, limitations and circumstances in which an alternative approach is necessary. * Establish principles for value attribution, proportionality, infrastructure dependency, public and private investment, commercial reasonableness and market practice. * Address the interaction between residential development value and land required for non-residential uses. * Provide a clear decision tree or process map showing how Homes England should select and apply the appropriate methodology. Workstream 3 - Asset-Type Application Guidance The framework shall include specific guidance for the following asset types, identifying the recommended valuation basis, evidence requirements, key adjustments and principal risks for each: * education land; * healthcare land and facilities; * public open space and community parks; * strategic green infrastructure; * community and cultural facilities; * emergency services land; * transport and rail infrastructure; * utilities and service infrastructure; and * other public-sector or enabling land uses. The Consultant shall identify which principles are common across all asset types and where materially different approaches are required. Workstream 4 - Costs, Obligations and Adjustments * Establish how strategic infrastructure costs, abnormal costs, mitigation, legal obligations, land assembly costs, programme impacts and delivery risk should be treated in valuation assessments. * Distinguish between costs that affect gross value, costs that may properly offset value uplift and costs that should be treated elsewhere in a development appraisal. * Address the treatment of timing, indexation, risk, contingency, phasing and double counting. * Provide worked examples or illustrative calculations sufficient to demonstrate application of the methodology. Workstream 5 - Consortium and Multi-Landowner Considerations * Advise on appropriate common assumptions where commercially sensitive information cannot be shared between developers. * Address differing developer appraisals, landowner positions, collaboration arrangements and governance structures. * Identify implications arising from Competition and Markets Authority considerations and data confidentiality. * Recommend practical governance, evidence and assurance arrangements to support consistent application of the methodology across a consortium. Service 2 - Network Rail Shared Value Assessment Workstream 6 - Network Rail Case Study and Valuation * Apply the recommended framework to the current Network Rail Shared Value discussions at Wychavon Town. * Assess the relevant existing land value and development value positions using available evidence. * Identify the extent to which value is attributable to Network Rail land, assets, rights or interventions. * Assess potential gross and net Shared Value and provide a reasoned value or range of values. * Identify the asset interventions and legal or operational dependencies that materially affect the assessment. * Provide sensitivity testing against the assumptions most likely to affect the outcome. * Clearly distinguish facts, assumptions, professional judgement and areas where further evidence is required. * Provide an independent opinion on the likely commercial position and recommendations for Homes England's negotiations with Network Rail. Workstream 7 - Network Rail Costs and Offsets The assessment shall identify and evaluate costs and deductions that may be relevant to any net Shared Value position, including where applicable: * strategic infrastructure costs; * rail enhancement and Network Rail asset works; * asset protection costs; * bridges, crossings and access arrangements; * operational railway land, permanent acquisition and temporary possession; * drainage, easements and statutory undertaker requirements; * abnormal development costs; * highways, utilities and environmental mitigation; * legal obligations, land assembly and programme impacts; and * any other relevant costs or benefits. The Consultant shall explain the basis on which each item is included or excluded, how it affects the assessment and how double counting is avoided. Workstream 8 - Existing Models and Assurance * Review existing financial modelling and viability work only to the extent necessary to ensure consistency of assumptions and avoid duplication. * Identify and explain material inconsistencies between the valuation assessment and other project models. * Set out an audit trail of source information, assumptions, adjustments and calculations. * Provide a proportionate quality assurance statement confirming the internal review undertaken by a suitably experienced senior valuer.

Notice Details

Publication & Lifecycle

Open Contracting ID
ocds-h6vhtk-079414
Publication Source
Find A Tender Service
Latest Notice
https://www.find-tender.service.gov.uk/Notice/102896-2026
Current Stage
Award
All Stages
Award

Procurement Classification

Notice Type
UK7 - Contract Details Notice
Procurement Type
Standard
Procurement Category
Services
Procurement Method
Selective
Procurement Method Details
Below threshold - award under framework
Tender Suitability
Not specified
Awardee Scale
Large

Common Procurement Vocabulary (CPV)

CPV Divisions

70 - Real estate services


CPV Codes

70000000 - Real estate services

Notice Value(s)

Tender Value
Not specified
Lots Value
Not specified
Awards Value
Not specified
Contracts Value
£60,000 Under £100K

Notice Dates

Publication Date
29 Oct 20262 weeks ago
Submission Deadline
Not specified
Future Notice Date
Not specified
Award Date
Not specified
Contract Period
6 Oct 2026 - 19 Aug 2027 6-12 months
Recurrence
Not specified

Notice Status

Tender Status
Complete
Lots Status
Complete
Awards Status
Active
Contracts Status
Active

Buyer & Supplier

Contracting Authority (Buyer)

Main Buyer
Homes England (the name adopted by the Homes and Communities Agency)
Contact Name
Available with D3 Tenders Premium →
Contact Email
Available with D3 Tenders Premium →
Contact Phone
Available with D3 Tenders Premium →

Buyer Location

Locality
NEWCASTLE UPON TYNE
Postcode
NE4 5BZ
Postcode Area
Newcastle upon Tyne
Country
England

Major Region (ITL 1)
TLC North East (England)
Basic Region (ITL 2)
TLC4 Northumberland, Durham and Tyne & Wear
Small Region (ITL 3)
TLC43 Tyneside
Delivery Location
Not specified

Local Authority
Newcastle upon Tyne
Electoral Ward
Arthur's Hill
Westminster Constituency
Newcastle upon Tyne Central and West

Supplier Information

Number of Suppliers
1
Supplier Name

Montagu Evans LLP

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

JSON Markdown

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

Loading OCDS record...