Notice Information
Notice Title
2675a - Design and Build of a Solvent Storage Area
Notice Description
The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.
Lot Information
Lot 1
The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.
Notice Details
Publication & Lifecycle
- Open Contracting ID
- ocds-r6ebe6-0000733257
- Publication Source
- Public Contracts Scotland
- Latest Notice
- https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=NOV493754
- Current Stage
- Award
- All Stages
- Tender, Award
Procurement Classification
- Notice Type
- PCS Notice - Website Contract Award Notice
- Procurement Type
- Framework
- Procurement Category
- Works
- Procurement Method
- Open
- Procurement Method Details
- Open procedure
- Tender Suitability
- Not specified
- Awardee Scale
- Large
Common Procurement Vocabulary (CPV)
- CPV Divisions
45 - Construction work
-
- CPV Codes
45000000 - Construction work
Notice Value(s)
- Tender Value
- £2,000,000 £1M-£10M
- Lots Value
- Not specified
- Awards Value
- Not specified
- Contracts Value
- £2,000,000 £1M-£10M
Notice Dates
- Publication Date
- 29 Nov 20232 years ago
- Submission Deadline
- 9 Jun 2023Expired
- Future Notice Date
- Not specified
- Award Date
- 11 Sep 20232 years ago
- Contract Period
- Not specified - Not specified
- Recurrence
- Not specified
Notice Status
- Tender Status
- Complete
- Lots Status
- Complete
- Awards Status
- Not Specified
- Contracts Status
- Active
Buyer & Supplier
Contracting Authority (Buyer)
- Main Buyer
- CENTRE FOR PROCESS INNOVATION LIMITED
- Contact Name
- Not specified
- Contact Email
- e-tendering@uk-cpi.com
- Contact Phone
- +44 1642455340
Buyer Location
- Locality
- REDCAR
- Postcode
- TS10 4RF
- Post Town
- Cleveland
- Country
- England
-
- Major Region (ITL 1)
- TLC North East (England)
- Basic Region (ITL 2)
- TLC3 Tees Valley
- Small Region (ITL 3)
- TLC32 South Teesside
- Delivery Location
- Not specified
-
- Local Authority
- Redcar and Cleveland
- Electoral Ward
- Dormanstown
- Westminster Constituency
- Redcar
Further Information
Notice Documents
-
https://www.publiccontractsscotland.gov.uk/NoticeDownload/DownloadDocument.aspx?id=MAY479339&idx=1
25th May 2023 - 2675a Tender Pack -
https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=MAY479339
2675a - Design and Build of a Solvent Storage Area - The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender. -
https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=NOV493754
2675a - Design and Build of a Solvent Storage Area - The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.
Open Contracting Data Standard (OCDS)
View full OCDS Record for this contracting process
The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.
{
"tag": [
"compiled"
],
"id": "ocds-r6ebe6-0000733257-2023-11-29T00:00:00Z",
"date": "2023-11-29T00:00:00Z",
"ocid": "ocds-r6ebe6-0000733257",
"initiationType": "tender",
"parties": [
{
"id": "org-35",
"name": "Tilbury Douglas Construction Ltd",
"identifier": {
"legalName": "Tilbury Douglas Construction Ltd"
},
"address": {
"streetAddress": "2 Almondview Business Park, , Almondview",
"locality": "Livingston",
"region": "UKM78",
"postalCode": "EH54 6SF"
},
"contactPoint": {
"email": "e-tendering@uk-cpi.com",
"telephone": "+44 1642455340",
"url": "https://www.publiccontractsscotland.gov.uk/Default.aspx"
},
"roles": [
"supplier"
],
"details": {
"classifications": [
{
"id": "Body governed by public law",
"scheme": "TED_CA_TYPE"
},
{
"id": "Scientific Research",
"scheme": "COFOG"
},
{
"id": "Research and Development",
"scheme": "COFOG"
}
],
"url": "http://",
"scale": "large"
}
},
{
"id": "org-36",
"name": "Glasgow Sheriff & Justice of the Peace Court",
"identifier": {
"legalName": "Glasgow Sheriff & Justice of the Peace Court"
},
"address": {
"streetAddress": "Sheriff Clerk's Office, 1 Carlton Place",
"locality": "Glasgow",
"postalCode": "G5 9DA"
},
"contactPoint": {
"url": "http://"
},
"roles": [
"reviewBody"
]
},
{
"id": "org-34",
"name": "Centre for Process Innovation Limited",
"identifier": {
"legalName": "Centre for Process Innovation Limited"
},
"address": {
"streetAddress": "Wilton Centre",
"locality": "Redcar",
"region": "UK",
"postalCode": "TS10 4RF"
},
"contactPoint": {
"email": "e-tendering@uk-cpi.com",
"telephone": "+44 1642455340",
"url": "http://"
},
"roles": [
"buyer",
"centralPurchasingBody"
],
"details": {
"classifications": [
{
"id": "Body governed by public law",
"scheme": "TED_CA_TYPE"
},
{
"id": "Scientific Research",
"scheme": "COFOG"
}
],
"url": "http://www.uk-cpi.com"
}
}
],
"buyer": {
"name": "Centre for Process Innovation Limited",
"id": "org-34"
},
"tender": {
"id": "2675a",
"title": "2675a - Design and Build of a Solvent Storage Area",
"description": "The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.",
"status": "complete",
"items": [
{
"id": "1",
"additionalClassifications": [
{
"id": "45000000",
"scheme": "CPV"
}
],
"deliveryAddresses": [
{
"region": "UK"
},
{
"region": "UK"
}
],
"relatedLot": "1"
}
],
"value": {
"amount": 2000000,
"currency": "GBP"
},
"procurementMethod": "open",
"procurementMethodDetails": "Open procedure",
"mainProcurementCategory": "works",
"submissionMethod": [
"electronicSubmission"
],
"submissionMethodDetails": "https://www.publiccontractsscotland.gov.uk/Default.aspx",
"tenderPeriod": {
"endDate": "2023-06-09T12:00:00Z"
},
"awardPeriod": {
"startDate": "2023-06-09T12:30:00Z"
},
"documents": [
{
"id": "MAY479339",
"documentType": "contractNotice",
"title": "2675a - Design and Build of a Solvent Storage Area",
"description": "The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.",
"url": "https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=MAY479339",
"format": "text/html"
},
{
"id": "MAY479339-1",
"title": "2675a Tender Pack",
"url": "https://www.publiccontractsscotland.gov.uk/NoticeDownload/DownloadDocument.aspx?id=MAY479339&idx=1",
"datePublished": "2023-05-25T10:25:52Z",
"dateModified": "2023-05-25T10:25:52Z",
"format": "application/x-zip-compressed"
},
{
"id": "NOV493754",
"documentType": "awardNotice",
"title": "2675a - Design and Build of a Solvent Storage Area",
"description": "The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.",
"url": "https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=NOV493754",
"format": "text/html"
}
],
"lots": [
{
"id": "1",
"description": "The Grand Challenge 3 manufacturing process will require a number of facility modifications to enable storage and transfer of solvent in and out of cleanroom 4 from the yard; extend utility lines to clean room 4; install process and emergency vent for the process from clean room 4 and link signals from new equipment into the BMS and EMS. The specific process equipment required for the Grand Challenge 3 will be procured by CPI as will 3 extract booths to house the process equipment. This tender is for the integration work surrounding the new process equipment and flow booths and for the appointed party to carry out the Principal Contractor and Principal Designer duties for this project. The work has been divided into 6 sections and it is expected that the principal contractor, or appointed sub-contractor(s) will deliver all of these sections. Please download the tender pack from https://www.publiccontractsscotland.gov.uk/Default.aspx for more information. Please note, as per the invitation to tender document, our estimated budget for this scope of work is 750,000.00 GBP, however, the total framework spend for this tender will be 2,000,000 GBP to cover any future requirements (if necessary) falling within the scope of the tender.",
"status": "complete",
"hasOptions": false,
"submissionTerms": {
"variantPolicy": "allowed"
},
"contractPeriod": {
"durationInDays": 1440
},
"hasRenewal": false
}
],
"bidOpening": {
"date": "2023-06-09T12:30:00Z"
},
"coveredBy": [
"GPA"
],
"submissionTerms": {
"languages": [
"en"
]
},
"classification": {
"id": "45000000",
"scheme": "CPV"
},
"hasRecurrence": false,
"techniques": {
"hasFrameworkAgreement": true
}
},
"language": "EN",
"description": "(SC Ref:751839)",
"links": [
{
"rel": "canonical",
"href": "https://api.publiccontractsscotland.gov.uk/v1/Notice?id=ocds-r6ebe6-0000733257"
},
{
"rel": "canonical",
"href": "https://api.publiccontractsscotland.gov.uk/v1/Notice?id=ocds-r6ebe6-0000733257"
}
],
"noticetype": "PCS Notice - Website Contract Award Notice",
"awards": [
{
"id": "2675a-1",
"suppliers": [
{
"id": "org-35",
"name": "Tilbury Douglas Construction Ltd"
}
],
"relatedLots": [
"1"
]
}
],
"contracts": [
{
"id": "2675a-1",
"awardID": "2675a-1",
"status": "active",
"value": {
"amount": 2000000,
"currency": "GBP"
},
"dateSigned": "2023-09-11T00:00:00Z"
}
],
"bids": {
"statistics": [
{
"id": "71",
"measure": "bids",
"value": 2,
"relatedLot": "1"
},
{
"id": "72",
"measure": "smeBids",
"value": 1,
"relatedLot": "1"
},
{
"id": "73",
"measure": "foreignBidsFromEU",
"value": 0,
"relatedLot": "1"
},
{
"id": "74",
"measure": "foreignBidsFromNonEU",
"value": 2,
"relatedLot": "1"
},
{
"id": "75",
"measure": "electronicBids",
"value": 2,
"relatedLot": "1"
}
]
}
}