Award

REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE)

THE TALL SHIP GLENLEE TRUST

This public procurement record has 3 releases in its history.

Award

10 Feb 2026 at 00:00

TenderUpdate

15 Jan 2026 at 00:00

Tender

17 Dec 2025 at 00:00

Summary of the contracting process

The Tall Ship Glenlee Trust undertook a public procurement process to procure and install a replacement disabled access lift on The Tall Ship Glenlee, located at 150 Pointhouse Place, Glasgow. The procurement falls under the industry category of recreation, culture and religion. The tender was processed using an open procedure method, categorised under goods, with the procurement process culminating in the award stage on 10th February 2026. The process was particularly accelerated, permitting a 15-day period, and was funded through the Museums Galleries Scotland Repair and Adaptation Fund. The contract was awarded to Saltire Lifts LTD, valued at GBP 51,829, with the work expected to start on 30th January 2026 and completed by 20th March 2026. The project requirements included a turnkey approach for the removal and installation of the lift, and significant insurance cover was mandated as part of the contract compliance.

This tender offers substantial business opportunities, particularly for companies specialising in accessibility solutions and maritime renovations. The project necessitates a platform lift with specific capabilities, making it ideal for businesses that design, supply, and install lifts in challenging environments such as historic or marine settings. Furthermore, due to the turnkey project requirements including design, removal, installation, and compliance with regulatory standards, businesses with a comprehensive skill set in turnkey projects or with experience in the maritime sector will find this contract to be an optimal fit. The inclusion of a five-year maintenance package and a five-year warranty on all parts signifies an ongoing business relationship, presenting opportunities for sustained business growth and expansion for the hired company.

Find more tenders on our Open Data Platform.
How relevant is this notice?

D3 Tenders Premium

Win More Public Sector Contracts

AI-powered tender discovery, pipeline management, and market intelligence — everything you need to grow your public sector business.

Notice Title

REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE)

Notice Description

The historic vessel, The Tall Ship Glenlee requires a replacement accessibility lift to be purchased and installed using funds from Museums Galleries Scotland Repair and Adaptation Fund. Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP 10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP 10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.

Lot Information

Lot 1

Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.

Publication & Lifecycle

Open Contracting ID
ocds-r6ebe6-0000818861
Publication Source
Public Contracts Scotland
Latest Notice
https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=FEB549258
Current Stage
Award
All Stages
Tender, Award

Procurement Classification

Notice Type
OJEU - F3 - Contract Award Notice
Procurement Type
Standard
Procurement Category
Goods
Procurement Method
Open
Procurement Method Details
Open procedure
Tender Suitability
Not specified
Awardee Scale
SME

Common Procurement Vocabulary (CPV)

CPV Divisions

42 - Industrial machinery


CPV Codes

42416000 - Lifts, skip hoists, hoists, escalators and moving walkways

42416100 - Lifts

42416120 - Goods lifts

42416130 - Mechanical lifts

42417000 - Elevators and conveyors

42419510 - Parts of lifts

Notice Value(s)

Tender Value
£70,000 Under £100K
Lots Value
£70,000 Under £100K
Awards Value
Not specified
Contracts Value
£51,829 Under £100K

Notice Dates

Publication Date
10 Feb 20261 weeks ago
Submission Deadline
16 Jan 2026Expired
Future Notice Date
Not specified
Award Date
10 Feb 20261 weeks ago
Contract Period
30 Jan 2026 - 13 Mar 2026 1-6 months
Recurrence
Not specified

Notice Status

Tender Status
Complete
Lots Status
Complete
Awards Status
Not Specified
Contracts Status
Active

Contracting Authority (Buyer)

Main Buyer
THE TALL SHIP GLENLEE TRUST
Contact Name
Fiona Greer
Contact Email
fiona.greer@thetallship.com
Contact Phone
+44 1413573699

Buyer Location

Locality
GLASGOW
Postcode
G3 8RS
Post Town
Glasgow
Country
Scotland

Major Region (ITL 1)
TLM Scotland
Basic Region (ITL 2)
TLM3 West Central Scotland
Small Region (ITL 3)
TLM32 Glasgow City
Delivery Location
TLM82 Glasgow City

Local Authority
Glasgow City
Electoral Ward
Anderston/City/Yorkhill
Westminster Constituency
Glasgow North

Supplier Information

Number of Suppliers
1
Supplier Name

SALTIRE LIFTS

Further Information

Notice Documents

  • https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=DEC545864
    REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE) - The historic vessel, The Tall Ship Glenlee requires a replacement accessibility lift to be purchased and installed using funds from Museums Galleries Scotland Repair and Adaptation Fund. Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP 10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP 10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.
  • https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=FEB549258
    REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE) - The historic vessel, The Tall Ship Glenlee requires a replacement accessibility lift to be purchased and installed using funds from Museums Galleries Scotland Repair and Adaptation Fund. Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP 10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP 10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

Download

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

{
    "tag": [
        "compiled"
    ],
    "id": "ocds-r6ebe6-0000818861-2026-02-10T00:00:00Z",
    "date": "2026-02-10T00:00:00Z",
    "ocid": "ocds-r6ebe6-0000818861",
    "initiationType": "tender",
    "parties": [
        {
            "id": "org-44",
            "name": "The Tall Ship Glenlee Trust",
            "identifier": {
                "legalName": "The Tall Ship Glenlee Trust"
            },
            "address": {
                "streetAddress": "150 Pointhouse Place",
                "locality": "Glasgow",
                "region": "UK",
                "postalCode": "G3 8RS"
            },
            "contactPoint": {
                "name": "Fiona Greer",
                "email": "fiona.greer@thetallship.com",
                "telephone": "+44 1413573699",
                "url": "http://www.thetallship.com"
            },
            "roles": [
                "buyer",
                "centralPurchasingBody"
            ],
            "details": {
                "classifications": [
                    {
                        "id": "Registered charity",
                        "scheme": "TED_CA_TYPE"
                    },
                    {
                        "id": "08",
                        "description": "Recreation, culture and religion",
                        "scheme": "COFOG"
                    }
                ],
                "url": "http://www.thetallship.com"
            }
        },
        {
            "id": "org-30",
            "name": "Glasgow Sheriff Court and Justice of the Peace Court",
            "identifier": {
                "legalName": "Glasgow Sheriff Court and Justice of the Peace Court"
            },
            "address": {
                "streetAddress": "Sheriff Clerk's Office, PO Box 23, 1 Carlton Place,",
                "locality": "Glasgow",
                "postalCode": "G5 9DA"
            },
            "contactPoint": {
                "telephone": "+44 1414298888",
                "url": "https://www.scotcourts.gov.uk/the-courts/court-locations/glasgow-sheriff-court-and-justice-of-the-peace-court"
            },
            "roles": [
                "reviewBody"
            ]
        },
        {
            "id": "org-10",
            "name": "The Tall Ship Glenlee Trust",
            "identifier": {
                "legalName": "The Tall Ship Glenlee Trust"
            },
            "address": {
                "streetAddress": "150 Pointhouse Place",
                "locality": "Glasgow",
                "region": "UK",
                "postalCode": "G3 8RS"
            },
            "contactPoint": {
                "name": "Fiona Greer",
                "email": "fiona.greer@thetallship.com",
                "telephone": "+44 1413573699",
                "url": "http://"
            },
            "roles": [
                "buyer"
            ],
            "details": {
                "url": "http://www.thetallship.com"
            }
        },
        {
            "id": "org-36",
            "name": "The Tall Ship Glenlee Trust",
            "identifier": {
                "legalName": "The Tall Ship Glenlee Trust"
            },
            "address": {
                "streetAddress": "150 Pointhouse Place",
                "locality": "Glasgow",
                "region": "UK",
                "postalCode": "G3 8RS"
            },
            "contactPoint": {
                "name": "Fiona Greer",
                "email": "fiona.greer@thetallship.com",
                "telephone": "+44 1413573699",
                "url": "http://"
            },
            "roles": [
                "buyer",
                "centralPurchasingBody"
            ],
            "details": {
                "classifications": [
                    {
                        "id": "Registered charity",
                        "scheme": "TED_CA_TYPE"
                    },
                    {
                        "id": "08",
                        "description": "Recreation, culture and religion",
                        "scheme": "COFOG"
                    }
                ],
                "url": "http://www.thetallship.com"
            }
        },
        {
            "id": "org-37",
            "name": "Saltire Lifts LTD",
            "identifier": {
                "legalName": "Saltire Lifts LTD"
            },
            "address": {
                "streetAddress": "The Atrium Business Centre, North Caldeen Road",
                "locality": "Coatbridge",
                "region": "UK",
                "postalCode": "ML5 4EF"
            },
            "contactPoint": {
                "telephone": "+44 7752153885"
            },
            "roles": [
                "supplier"
            ],
            "details": {
                "scale": "sme",
                "url": "http://"
            }
        },
        {
            "id": "org-38",
            "name": "Glasgow Sheriff Court and Justice of the Peace Court",
            "identifier": {
                "legalName": "Glasgow Sheriff Court and Justice of the Peace Court"
            },
            "address": {
                "locality": "Glasgow"
            },
            "contactPoint": {
                "url": "http://"
            },
            "roles": [
                "reviewBody"
            ]
        }
    ],
    "buyer": {
        "name": "The Tall Ship Glenlee Trust",
        "id": "org-36"
    },
    "tender": {
        "id": "ocds-r6ebe6-0000818861",
        "title": "REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE)",
        "description": "The historic vessel, The Tall Ship Glenlee requires a replacement accessibility lift to be purchased and installed using funds from Museums Galleries Scotland Repair and Adaptation Fund. Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP 10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP 10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.",
        "status": "complete",
        "items": [
            {
                "id": "1",
                "additionalClassifications": [
                    {
                        "id": "42416000",
                        "scheme": "CPV"
                    },
                    {
                        "id": "42416100",
                        "scheme": "CPV"
                    },
                    {
                        "id": "42416120",
                        "scheme": "CPV"
                    },
                    {
                        "id": "42416130",
                        "scheme": "CPV"
                    },
                    {
                        "id": "42419510",
                        "scheme": "CPV"
                    },
                    {
                        "id": "42417000",
                        "scheme": "CPV"
                    }
                ],
                "deliveryLocation": {
                    "description": "The Tall Ship Glenlee, 150 Pointhouse Place, Glasgow, G3 8RS"
                },
                "deliveryAddresses": [
                    {
                        "region": "UKM82"
                    },
                    {
                        "region": "UKM82"
                    }
                ],
                "relatedLot": "1"
            }
        ],
        "value": {
            "amount": 70000,
            "currency": "GBP"
        },
        "procurementMethod": "open",
        "procurementMethodDetails": "Open procedure",
        "mainProcurementCategory": "goods",
        "submissionMethod": [
            "electronicSubmission",
            "written"
        ],
        "submissionMethodDetails": "http://www.thetallship.com",
        "tenderPeriod": {
            "endDate": "2026-01-16T12:00:00Z"
        },
        "awardPeriod": {
            "startDate": "2026-01-23T12:00:00Z"
        },
        "documents": [
            {
                "id": "DEC545864",
                "documentType": "contractNotice",
                "title": "REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE)",
                "description": "The historic vessel, The Tall Ship Glenlee requires a replacement accessibility lift to be purchased and installed using funds from Museums Galleries Scotland Repair and Adaptation Fund. Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP 10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP 10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.",
                "url": "https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=DEC545864",
                "format": "text/html"
            },
            {
                "id": "FEB549258",
                "documentType": "awardNotice",
                "title": "REPLACEMENT DISABLED ACCESS LIFT FOR SV GLENLEE (THE TALL SHIP GLENLEE)",
                "description": "The historic vessel, The Tall Ship Glenlee requires a replacement accessibility lift to be purchased and installed using funds from Museums Galleries Scotland Repair and Adaptation Fund. Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP 10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP 10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.",
                "url": "https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=FEB549258",
                "format": "text/html"
            }
        ],
        "lots": [
            {
                "id": "1",
                "description": "Contractor turnkey project requirement definition:- 1. Lift as presently configured with four access/ egress levels in weather deckhouse, 'tween decks, mezzanine deck, hold, DDA compliant. 2. Platform lift capable of carrying a minimum load of 450kg and have a capacity alternatively for 5 persons. 3. Power - single phase 220 V AC. 4. Capable of operation in up to 2 degrees of ship list and 1 degree change of fore and aft trim of ship. 5. Does not need to meet fire evacuation requirements. 6. Design must accommodate the limited pit depth of <150mm. 7. Meet or exceed 2006/42CE. 8. All works must comply with CDM regs. 9. Lift must be capable of a minimum of 20 operational cycles per hour. 10. Normal duty cycle is 8 hours per day with some operational days of up to 24 hours per day. 11. A five-year warranty on all parts and labour/ hours is required. 12. A five-year maintenance package is required. 13. A key control is required to avoid unauthorised operations. 14. Turnkey project for removal of all components of old lift installation and installation and commissioning of new lift. 15. All responsibility for measurements, design, removal of old equipment and materials arisings from site. 16. All transportation of equipment and materials, lifting and craneage are part of the turnkey contract. 17. All works must comply with relevant Health and Safety at Work Act requirements. 18. Insurance must be provided for a sum of GBP10 million pounds for any one occurrence. 19. Product liability insurance in the sum of GBP10 million pounds in the aggregate and professional indemnity insurance in the aggregate. Client site works: - Works on essential support steel substructures for lift in lower hull steelwork blasting inspection, any necessary strengthening and protective coating whilst old lift removed must be completed before new lift installation.",
                "status": "complete",
                "value": {
                    "amount": 70000,
                    "currency": "GBP"
                },
                "awardCriteria": {
                    "criteria": [
                        {
                            "type": "quality",
                            "name": "Quality",
                            "description": "20"
                        },
                        {
                            "type": "price",
                            "description": "20"
                        },
                        {
                            "type": "quality",
                            "name": "Quality",
                            "description": "20"
                        },
                        {
                            "type": "price",
                            "description": "20"
                        }
                    ]
                },
                "hasOptions": false,
                "submissionTerms": {
                    "variantPolicy": "notAllowed"
                },
                "contractPeriod": {
                    "startDate": "2026-01-30T00:00:00Z",
                    "endDate": "2026-03-13T00:00:00Z"
                },
                "hasRenewal": false
            }
        ],
        "bidOpening": {
            "date": "2026-01-23T12:00:00Z"
        },
        "coveredBy": [
            "GPA"
        ],
        "procedure": {
            "isAccelerated": true,
            "acceleratedRationale": "We are ok with 15 days"
        },
        "submissionTerms": {
            "languages": [
                "en"
            ],
            "bidValidityPeriod": {
                "endDate": "2026-02-16T00:00:00Z"
            }
        },
        "classification": {
            "id": "42416100",
            "scheme": "CPV"
        },
        "hasRecurrence": false,
        "legalBasis": {
            "id": "32014L0024",
            "scheme": "CELEX"
        },
        "amendments": [
            {
                "id": "amd-12",
                "description": "No notes of interest so far",
                "unstructuredChanges": [
                    {
                        "oldValue": {
                            "date": "2026-01-16T12:00:00Z"
                        },
                        "newValue": {
                            "date": "2026-01-23T12:00:00Z"
                        },
                        "where": {
                            "section": "IV.2.2",
                            "label": "Time limit"
                        }
                    },
                    {
                        "oldValue": {
                            "date": "2026-01-30T00:00:00Z"
                        },
                        "newValue": {
                            "date": "2026-02-06T00:00:00Z"
                        },
                        "where": {
                            "section": "II.2.7",
                            "label": "Duration Start"
                        }
                    },
                    {
                        "oldValue": {
                            "date": "2026-03-13T00:00:00Z"
                        },
                        "newValue": {
                            "date": "2026-03-20T00:00:00Z"
                        },
                        "where": {
                            "section": "II.2.7",
                            "label": "Duration End"
                        }
                    },
                    {
                        "oldValue": {
                            "date": "2026-02-16T00:00:00Z"
                        },
                        "newValue": {
                            "date": "2026-02-23T00:00:00Z"
                        },
                        "where": {
                            "section": "IV.2.6",
                            "label": "Minimum time frame during which the tenderer must maintain the tender"
                        }
                    },
                    {
                        "oldValue": {
                            "date": "2026-01-23T12:00:00Z"
                        },
                        "newValue": {
                            "date": "2026-01-30T12:00:00Z"
                        },
                        "where": {
                            "section": "IV.2.7",
                            "label": "Conditions for opening of tenders"
                        }
                    }
                ]
            }
        ]
    },
    "language": "EN",
    "description": "(SC Ref:823292)",
    "links": [
        {
            "rel": "canonical",
            "href": "https://api.publiccontractsscotland.gov.uk/v1/Notice?id=ocds-r6ebe6-0000818861"
        },
        {
            "rel": "canonical",
            "href": "https://api.publiccontractsscotland.gov.uk/v1/Notice?id=ocds-r6ebe6-0000818861"
        },
        {
            "rel": "canonical",
            "href": "https://api.publiccontractsscotland.gov.uk/v1/Notice?id=ocds-r6ebe6-0000818861"
        }
    ],
    "noticetype": "OJEU - F3 - Contract Award Notice",
    "awards": [
        {
            "id": "ocds-r6ebe6-0000818861-1",
            "suppliers": [
                {
                    "id": "org-37",
                    "name": "Saltire Lifts LTD"
                }
            ],
            "relatedLots": [
                "1"
            ]
        }
    ],
    "contracts": [
        {
            "id": "ocds-r6ebe6-0000818861-1",
            "awardID": "ocds-r6ebe6-0000818861-1",
            "status": "active",
            "value": {
                "amount": 51829,
                "currency": "GBP"
            },
            "dateSigned": "2026-02-10T00:00:00Z"
        }
    ],
    "relatedProcesses": [
        {
            "id": "1",
            "relationship": [
                "planning"
            ],
            "scheme": "EU-OJ",
            "identifier": "2025/S 000-083806"
        }
    ],
    "bids": {
        "statistics": [
            {
                "id": "61",
                "measure": "bids",
                "value": 3,
                "relatedLot": "1"
            },
            {
                "id": "62",
                "measure": "smeBids",
                "value": 2,
                "relatedLot": "1"
            },
            {
                "id": "63",
                "measure": "foreignBidsFromEU",
                "value": 0,
                "relatedLot": "1"
            },
            {
                "id": "64",
                "measure": "foreignBidsFromNonEU",
                "value": 3,
                "relatedLot": "1"
            },
            {
                "id": "65",
                "measure": "electronicBids",
                "value": 3,
                "relatedLot": "1"
            }
        ]
    }
}