Contract Summary
The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages. Due to budget constraints, the Council are considering 3 options, these being: - • Option A: All Concrete Works Only Concrete works only. No removal of any of the timber landing stages. • Option B: All Concrete Works and Part Timber Landing Stage Removal Concrete works and the complete removal of the Northern and Small Boat timber landing stages only. • Option C: All Concrete Works and All Timber Landing Stage Removal Concrete works and complete removal of all of the timber landing stages All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works). The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn't affordable then Option A. Suppliers can bid to any or all of the 3 options. The specifications which outline the requirements for this contract are contained with the following document 'Bournemouth Pier Structural Works - Document Schedule 16.01.2025' The successful Bidder will be expected to commence the works in May 2025 and will be required to ensure the works are completed by December 2026 (not including defects period). Additional information: Suppliers interested in this opportunity can access the full procurement documentation by visiting BCP Council's Tendering system www.supplyingthesouthwest.org.uk Suppliers should search for the opportunity through Supplying the South West. There are further details of the opportunity on the advert published on www.supplyingthesouthwest.org.uk and instructions on how suppliers can access the procurement documentation for completion. Responses to the opportunity must be submitted electronically through www.supplyingthesouthwest.org.uk before the deadline shown on the system. If you are unable to access the advert for the opportunity through www.supplyingthesouthwest.org.uk please contact the Council using the contact details provided.
-
Contract Details
- Open Contracting ID
-
ocds-b5fd17-5eeac1a0-163b-400d-ab06-84c57ce002b0
- Publication Source
-
Contracts Finder
- Procurement Stage
-
Tender
- Procurement Method
-
Open
- Procurement Method Details
-
Open Procedure (above Threshold)
- Procurement Category
-
Works
- Tender Suitability
-
SME
- Framework / DPS
-
Contract Classification
- CPV Code(s)
-
45220000
45223000
45223500
45241300
45243300
45262330 - CPV Division(s)
-
45 - Construction work
-
Awarding Authority
BOURNEMOUTH CHRISTCHURCH AND POOLE COUNCIL
- Buyer Name
-
Strategic Procurement Team
- Buyer Email
-
procurement@bcpcouncil.gov.uk
- Buyer Phone
-
+44 1202128989
- Buyer Address
-
BCP Council, Civic Centre, Bourne Avenue
Bournemouth
BH2 6DY
England
-
Contract Timeline
- Publication Date
-
5th February 2025 17:49:38 PM
- Tender Deadline
-
21st March 2025 14:00:00 PM Expired
-
Contract Summary
The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages. Due to budget constraints, the Council are considering 3 options, these being: - • Option A: All Concrete Works Only Concrete works only. No removal of any of the timber landing stages. • Option B: All Concrete Works and Part Timber Landing Stage Removal Concrete works and the complete removal of the Northern and Small Boat timber landing stages only. • Option C: All Concrete Works and All Timber Landing Stage Removal Concrete works and complete removal of all of the timber landing stages All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works). The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn't affordable then Option A. Suppliers can bid to any or all of the 3 options. The specifications which outline the requirements for this contract are contained with the following document 'Bournemouth Pier Structural Works - Document Schedule 16.01.2025' The successful Bidder will be expected to commence the works in May 2025 and will be required to ensure the works are completed by December 2026 (not including defects period). Additional information: Suppliers interested in this opportunity can access the full procurement documentation by visiting BCP Council's Tendering system www.supplyingthesouthwest.org.uk Suppliers should search for the opportunity through Supplying the South West. There are further details of the opportunity on the advert published on www.supplyingthesouthwest.org.uk and instructions on how suppliers can access the procurement documentation for completion. Responses to the opportunity must be submitted electronically through www.supplyingthesouthwest.org.uk before the deadline shown on the system. If you are unable to access the advert for the opportunity through www.supplyingthesouthwest.org.uk please contact the Council using the contact details provided.
-
Contract Details
- Open Contracting ID
-
ocds-b5fd17-5eeac1a0-163b-400d-ab06-84c57ce002b0
- Publication Source
-
Contracts Finder
- Procurement Stage
-
Tender
- Procurement Method
-
Open
- Procurement Method Details
-
Open Procedure (above Threshold)
- Procurement Category
-
Works
- Tender Suitability
-
SME
- Framework / DPS
-
Contract Classification
- CPV Code(s)
-
45220000
45223000
45223500
45241300
45243300
45262330 - CPV Division(s)
-
45 - Construction work
-
Awarding Authority
BOURNEMOUTH CHRISTCHURCH AND POOLE COUNCIL
- Buyer Name
-
Strategic Procurement Team
- Buyer Email
-
procurement@bcpcouncil.gov.uk
- Buyer Phone
-
+44 1202128989
- Buyer Address
-
BCP Council, Civic Centre, Bourne Avenue
Bournemouth
BH2 6DY
England
-
Contract Timeline
- Publication Date
-
20th January 2025 14:08:33 PM
- Tender Deadline
-
28th February 2025 14:00:00 PM Expired
-
Contract Summary
The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages. Due to budget constraints, the Council are considering 3 options, these being: - • Option A: All Concrete Works Only Concrete works only. No removal of any of the timber landing stages. • Option B: All Concrete Works and Part Timber Landing Stage Removal Concrete works and the complete removal of the Northern and Small Boat timber landing stages only. • Option C: All Concrete Works and All Timber Landing Stage Removal Concrete works and complete removal of all of the timber landing stages All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works). The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn't affordable then Option A. Suppliers can bid to any or all of the 3 options. The specifications which outline the requirements for this contract are contained with the following document 'Bournemouth Pier Structural Works - Document Schedule 16.01.2025' The successful Bidder will be expected to commence the works in May 2025 and will be required to ensure the works are completed by December 2026 (not including defects period). Additional information: Suppliers interested in this opportunity can access the full procurement documentation by visiting BCP Council's Tendering system www.supplyingthesouthwest.org.uk Suppliers should search for the opportunity through Supplying the South West. There are further details of the opportunity on the advert published on www.supplyingthesouthwest.org.uk and instructions on how suppliers can access the procurement documentation for completion. Responses to the opportunity must be submitted electronically through www.supplyingthesouthwest.org.uk before the deadline shown on the system. If you are unable to access the advert for the opportunity through www.supplyingthesouthwest.org.uk please contact the Council using the contact details provided.
-
Contract Details
- Open Contracting ID
-
ocds-b5fd17-5eeac1a0-163b-400d-ab06-84c57ce002b0
- Publication Source
-
Contracts Finder
- Procurement Stage
-
Tender
- Procurement Method
-
Open
- Procurement Method Details
-
Open Procedure (above Threshold)
- Procurement Category
-
Works
- Tender Suitability
-
SME
- Framework / DPS
-
Contract Classification
- CPV Code(s)
-
45220000
45223000
45223500
45241300
45243300
45262330 - CPV Division(s)
-
45 - Construction work
-
Awarding Authority
BOURNEMOUTH CHRISTCHURCH AND POOLE COUNCIL
- Buyer Name
-
Strategic Procurement Team
- Buyer Email
-
procurement@bcpcouncil.gov.uk
- Buyer Phone
-
+44 1202128989
- Buyer Address
-
BCP Council, Civic Centre, Bourne Avenue
Bournemouth
BH2 6DY
England