Award

Decarbonisation Programme - Project CoPPA

NETWORK RAIL INFRASTRUCTURE LTD

This public procurement record has 2 releases in its history.

AwardUpdate

27 Jul 2023 at 14:43

Award

19 Jun 2023 at 15:45

Summary of the contracting process

The Network Rail Infrastructure Ltd has awarded EDF Energy Renewables Ltd a contract titled "Decarbonisation Programme - Project CoPPA" on 27th July 2023. This procurement falls under the goods category and involves a national contract to supply renewable electricity over 15 years. The contract value is £79.80 million, with the supplier guaranteeing a minimum technical availability of 93%. The contract involves a corporate power purchase agreement (cPPA) and a solar PV facility construction project in the UK.

This contract presents growth opportunities for businesses in the renewable energy sector. Companies with expertise in electricity, solar energy, and renewable technologies would be well-suited to compete. The procurement stage is complete, and key deadlines include the final investment decision milestone by 30th September 2023. Located in London, this contract offers potential for businesses to contribute to the decarbonisation goals of Network Rail Infrastructure Ltd through the supply of renewable electricity.

Find more tenders on our Open Data Platform.
How relevant is this notice?

D3 Tenders Premium

Win More Public Sector Contracts

AI-powered tender discovery, pipeline management, and market intelligence — everything you need to grow your public sector business.

Notice Title

Decarbonisation Programme - Project CoPPA

Notice Description

The procurement falls outside the scope of application of the regulations Explanation: This notice relates to a permitted modification to revise the price of a corporate power purchase agreement (the cPPA) originally awarded on 28 July 2022, following a competitive award process using the negotiated procedure in accordance with the Utilities Contracts Regulations 2016 (UCR). The cPPA is a national contract for the supply to NR of a target P50 volume of 63.8GWh per annum of renewable electricity for 15 years. The renewable electricity will be generated by a solar PV facility to be constructed, operated and maintained by the supplier. The solar PV facility will have a target installed capacity of 60 MWp +- 10%, with the supplier guaranteeing a minimum technical availability of 93%. The renewable electricity to be supplied to NR under the cPPA will be supplied on an "as available" basis using a sleeving arrangement with a third party licensed electricity supplier and the relevant volumes supplied will be utilised by NR's non-traction business (e.g. managed stations, offices and depots). Please note that certain of the core supplier requirements referred to above differ from those listed in the contract award notice published on 19 August 2022 as the core supplier requirements stated herein represent the final core supplier requirements in the executed cPPA entered into between NR and the supplier on 28 July 2022. The cPPA was made conditional on the supplier achieving a final investment decision (FID) by 31 March 2023 (FID Milestone Delivery Date). Following a series of successive, substantial and unforeseen rises in the European Central Bank (ECB) interest rates for Main Refinancing Operations (fixed rate tenders) over the period from 30 November 2021 to 12 May 2022, the underlying financial model supporting the original cPPA pricing could no longer produce a return on investment for the supplier to reach FID. Accordingly, the supplier has proposed, and NR has agreed to make, a revision to the total price of the cPPA that results in an increase of under 50%, from PS53.32 million to PS79.80 million. The price increase involves the ECB interest rates increasing from 0% in November 2021 to 3.75% in May 2023.. There will also be a new FID Milestone Delivery Date of 30 September 2023 in the revised cPPA. NR is revising the cPPA through a variation agreement. The revision of the cPPA by NR is a permitted modification under the UCR. It is permitted by the exemption in Regulation 88(1)(c). For completeness, and to maximise transparency, NR will also publish a modification notice under Regulation 88(2) in due course after the variation agreement is entered into.

Lot Information

Decarbonisation Programme - Project CoPPA

This notice relates to a permitted modification to revise the price of a corporate power purchase agreement (the cPPA) originally awarded on 28 July 2022, following a competitive award process using the negotiated procedure in accordance with the Utilities Contracts Regulations 2016 (UCR). The cPPA is a national contract for the supply to NR of a target P50 volume of 63.8GWh per annum of renewable electricity for 15 years. The renewable electricity will be generated by a solar PV facility to be constructed, operated and maintained by the supplier. The solar PV facility will have a target installed capacity of 60 MWp +- 10%, with the supplier guaranteeing a minimum technical availability of 93%. The renewable electricity to be supplied to NR under the cPPA will be supplied on an "as available" basis using a sleeving arrangement with a third party licensed electricity supplier and the relevant volumes supplied will be utilised by NR's non-traction business (e.g. managed stations, offices and depots).

Procurement Information

See II.2.4) Description of the procurement for explanation.

Publication & Lifecycle

Open Contracting ID
ocds-h6vhtk-03d7a7
Publication Source
Find A Tender Service
Latest Notice
https://www.find-tender.service.gov.uk/Notice/021864-2023
Current Stage
Award
All Stages
Award

Procurement Classification

Notice Type
Award Notice
Procurement Type
Standard
Procurement Category
Goods
Procurement Method
Limited
Procurement Method Details
Award procedure without prior publication of a call for competition
Tender Suitability
Not specified
Awardee Scale
Large

Common Procurement Vocabulary (CPV)

CPV Divisions

09 - Petroleum products, fuel, electricity and other sources of energy


CPV Codes

09300000 - Electricity, heating, solar and nuclear energy

09310000 - Electricity

Notice Value(s)

Tender Value
Not specified
Lots Value
Not specified
Awards Value
Not specified
Contracts Value
£79,800,000 £10M-£100M

Notice Dates

Publication Date
27 Jul 20232 years ago
Submission Deadline
Not specified
Future Notice Date
Not specified
Award Date
15 Jun 20223 years ago
Contract Period
Not specified - Not specified
Recurrence
Not specified

Notice Status

Tender Status
Complete
Lots Status
Not Specified
Awards Status
Active
Contracts Status
Active

Contracting Authority (Buyer)

Main Buyer
NETWORK RAIL INFRASTRUCTURE LTD
Contact Name
Not specified
Contact Email
nikki.hunter@networkrail.co.uk
Contact Phone
+44 1908781000

Buyer Location

Locality
LONDON
Postcode
SE1 8SW
Post Town
South East London
Country
England

Major Region (ITL 1)
TLI London
Basic Region (ITL 2)
TLI4 Inner London - East
Small Region (ITL 3)
TLI45 Lambeth
Delivery Location
Not specified

Local Authority
Lambeth
Electoral Ward
Waterloo & South Bank
Westminster Constituency
Vauxhall and Camberwell Green

Supplier Information

Number of Suppliers
1
Supplier Name

EDF ENERGY RENEWABLES

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

Download

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

{
    "tag": [
        "compiled"
    ],
    "id": "ocds-h6vhtk-03d7a7-2023-07-27T15:43:01+01:00",
    "date": "2023-07-27T15:43:01+01:00",
    "ocid": "ocds-h6vhtk-03d7a7",
    "description": "This notice relates to a permitted modification to revise the price of a corporate power purchase agreement (the cPPA) originally awarded on 28 July 2022, following a competitive award process using the negotiated procedure in accordance with the Utilities Contracts Regulations 2016 (UCR). A voluntary ex antre transparency notice in respect of this modification was published on 19 June (Reference: 2023/S 000-017404).",
    "initiationType": "tender",
    "tender": {
        "id": "ocds-h6vhtk-03d7a7",
        "legalBasis": {
            "id": "32014L0025",
            "scheme": "CELEX"
        },
        "title": "Decarbonisation Programme - Project CoPPA",
        "status": "complete",
        "classification": {
            "scheme": "CPV",
            "id": "09300000",
            "description": "Electricity, heating, solar and nuclear energy"
        },
        "mainProcurementCategory": "goods",
        "description": "The procurement falls outside the scope of application of the regulations Explanation: This notice relates to a permitted modification to revise the price of a corporate power purchase agreement (the cPPA) originally awarded on 28 July 2022, following a competitive award process using the negotiated procedure in accordance with the Utilities Contracts Regulations 2016 (UCR). The cPPA is a national contract for the supply to NR of a target P50 volume of 63.8GWh per annum of renewable electricity for 15 years. The renewable electricity will be generated by a solar PV facility to be constructed, operated and maintained by the supplier. The solar PV facility will have a target installed capacity of 60 MWp +- 10%, with the supplier guaranteeing a minimum technical availability of 93%. The renewable electricity to be supplied to NR under the cPPA will be supplied on an \"as available\" basis using a sleeving arrangement with a third party licensed electricity supplier and the relevant volumes supplied will be utilised by NR's non-traction business (e.g. managed stations, offices and depots). Please note that certain of the core supplier requirements referred to above differ from those listed in the contract award notice published on 19 August 2022 as the core supplier requirements stated herein represent the final core supplier requirements in the executed cPPA entered into between NR and the supplier on 28 July 2022. The cPPA was made conditional on the supplier achieving a final investment decision (FID) by 31 March 2023 (FID Milestone Delivery Date). Following a series of successive, substantial and unforeseen rises in the European Central Bank (ECB) interest rates for Main Refinancing Operations (fixed rate tenders) over the period from 30 November 2021 to 12 May 2022, the underlying financial model supporting the original cPPA pricing could no longer produce a return on investment for the supplier to reach FID. Accordingly, the supplier has proposed, and NR has agreed to make, a revision to the total price of the cPPA that results in an increase of under 50%, from PS53.32 million to PS79.80 million. The price increase involves the ECB interest rates increasing from 0% in November 2021 to 3.75% in May 2023.. There will also be a new FID Milestone Delivery Date of 30 September 2023 in the revised cPPA. NR is revising the cPPA through a variation agreement. The revision of the cPPA by NR is a permitted modification under the UCR. It is permitted by the exemption in Regulation 88(1)(c). For completeness, and to maximise transparency, NR will also publish a modification notice under Regulation 88(2) in due course after the variation agreement is entered into.",
        "lots": [
            {
                "id": "1",
                "description": "This notice relates to a permitted modification to revise the price of a corporate power purchase agreement (the cPPA) originally awarded on 28 July 2022, following a competitive award process using the negotiated procedure in accordance with the Utilities Contracts Regulations 2016 (UCR). The cPPA is a national contract for the supply to NR of a target P50 volume of 63.8GWh per annum of renewable electricity for 15 years. The renewable electricity will be generated by a solar PV facility to be constructed, operated and maintained by the supplier. The solar PV facility will have a target installed capacity of 60 MWp +- 10%, with the supplier guaranteeing a minimum technical availability of 93%. The renewable electricity to be supplied to NR under the cPPA will be supplied on an \"as available\" basis using a sleeving arrangement with a third party licensed electricity supplier and the relevant volumes supplied will be utilised by NR's non-traction business (e.g. managed stations, offices and depots).",
                "hasOptions": false,
                "title": "Decarbonisation Programme - Project CoPPA",
                "contractPeriod": {
                    "durationInDays": 5400
                }
            }
        ],
        "items": [
            {
                "id": "1",
                "additionalClassifications": [
                    {
                        "scheme": "CPV",
                        "id": "09310000",
                        "description": "Electricity"
                    }
                ],
                "deliveryAddresses": [
                    {
                        "region": "UK"
                    },
                    {
                        "region": "UK"
                    }
                ],
                "deliveryLocation": {
                    "description": "Throughout the UK"
                },
                "relatedLot": "1"
            }
        ],
        "procurementMethod": "limited",
        "procurementMethodDetails": "Award procedure without prior publication of a call for competition",
        "procurementMethodRationaleClassifications": [
            {
                "scheme": "TED_PT_AWARD_CONTRACT_WITHOUT_CALL",
                "id": "D_OUTSIDE_SCOPE",
                "description": "The procurement falls outside the scope of application of the directive"
            }
        ],
        "procurementMethodRationale": "See II.2.4) Description of the procurement for explanation."
    },
    "awards": [
        {
            "id": "017404-2023-1",
            "relatedLots": [
                "1"
            ],
            "status": "active",
            "hasSubcontracting": true,
            "suppliers": [
                {
                    "id": "GB-FTS-85522",
                    "name": "EDF Energy Renewables Ltd"
                }
            ]
        },
        {
            "id": "021864-2023-ecm_37803-1",
            "relatedLots": [
                "1"
            ],
            "title": "Decarbonisation Programme - Project CoPPA",
            "status": "active",
            "suppliers": [
                {
                    "id": "GB-FTS-88503",
                    "name": "EDF Energy Renewables Ltd"
                }
            ]
        }
    ],
    "parties": [
        {
            "id": "GB-FTS-85378",
            "name": "Network Rail Infrastructure Ltd",
            "identifier": {
                "legalName": "Network Rail Infrastructure Ltd",
                "id": "2904587"
            },
            "address": {
                "streetAddress": "Waterloo General Offices",
                "locality": "London",
                "region": "UK",
                "postalCode": "SE1 8SW",
                "countryName": "United Kingdom"
            },
            "contactPoint": {
                "telephone": "+44 1908781000",
                "email": "Nikki.Hunter@networkrail.co.uk"
            },
            "roles": [
                "buyer"
            ],
            "details": {
                "url": "http://www.networkrail.co.uk",
                "buyerProfile": "http://www.networkrail.co.uk",
                "classifications": [
                    {
                        "scheme": "TED_CE_ACTIVITY",
                        "id": "RAILWAY_SERVICES",
                        "description": "Railway services"
                    }
                ]
            }
        },
        {
            "id": "GB-FTS-85522",
            "name": "EDF Energy Renewables Ltd",
            "identifier": {
                "legalName": "EDF Energy Renewables Ltd",
                "id": "06456689"
            },
            "address": {
                "streetAddress": "Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring",
                "locality": "Sunderland",
                "region": "UK",
                "postalCode": "DH4 5RA",
                "countryName": "United Kingdom"
            },
            "roles": [
                "supplier"
            ],
            "details": {
                "scale": "large"
            }
        },
        {
            "id": "GB-FTS-85523",
            "name": "The High Court",
            "identifier": {
                "legalName": "The High Court"
            },
            "address": {
                "streetAddress": "Little George St, London Town",
                "locality": "London",
                "postalCode": "SW1P 3BD",
                "countryName": "United Kingdom"
            },
            "roles": [
                "reviewBody"
            ]
        },
        {
            "id": "GB-FTS-88503",
            "name": "EDF Energy Renewables Ltd",
            "identifier": {
                "legalName": "EDF Energy Renewables Ltd",
                "id": "0645668"
            },
            "address": {
                "streetAddress": "Alexander House, 1 Mandarin Road, Rainton Bridge Business Park, Houghton Le Spring",
                "locality": "Sunderland",
                "region": "UK",
                "postalCode": "DH4 5RA",
                "countryName": "United Kingdom"
            },
            "roles": [
                "supplier"
            ],
            "details": {
                "scale": "large"
            }
        },
        {
            "id": "GB-FTS-88504",
            "name": "The High Court",
            "identifier": {
                "legalName": "The High Court"
            },
            "address": {
                "streetAddress": "Little George Street",
                "locality": "London",
                "postalCode": "SW1P 3BD",
                "countryName": "United Kingdom"
            },
            "roles": [
                "reviewBody"
            ]
        }
    ],
    "buyer": {
        "id": "GB-FTS-85378",
        "name": "Network Rail Infrastructure Ltd"
    },
    "contracts": [
        {
            "id": "017404-2023-1",
            "awardID": "017404-2023-1",
            "status": "active",
            "dateSigned": "2023-06-16T00:00:00+01:00"
        },
        {
            "id": "021864-2023-ecm_37803-1",
            "awardID": "021864-2023-ecm_37803-1",
            "title": "Decarbonisation Programme - Project CoPPA",
            "status": "active",
            "value": {
                "amount": 79800000,
                "currency": "GBP"
            },
            "dateSigned": "2022-06-16T00:00:00+01:00",
            "period": {
                "durationInDays": 5400
            },
            "items": [
                {
                    "id": "1",
                    "title": "Decarbonisation Programme - Project CoPPA",
                    "classification": {
                        "scheme": "CPV",
                        "id": "09300000",
                        "description": "Electricity, heating, solar and nuclear energy"
                    },
                    "additionalClassifications": [
                        {
                            "scheme": "CPV",
                            "id": "09310000",
                            "description": "Electricity"
                        }
                    ],
                    "deliveryAddresses": [
                        {
                            "region": "UK"
                        }
                    ],
                    "relatedLot": "1"
                }
            ],
            "amendments": [
                {
                    "id": "1",
                    "description": "See II.2.4) Description of the procurement for explanation.",
                    "rationale": "Need for modification brought about by circumstances which a diligent contracting authority/entity could not foresee: See II.2.4) Description of the procurement for explanation."
                }
            ]
        }
    ],
    "language": "en"
}