TenderUpdate

Flood Cell 06, Snape Maltings

EAST SUFFOLK WATER MANAGEMENT BOARD

  • Contract Timeline

    Publication Date

    17th April 2025 11:10:06 AM

  • Contract Summary

    The Upper Alde & Ore Estuary Embankment Improvements scheme will reduce tidal flood riskand enhance the environment in the Upper Alde and Ore Estuary. The Alde and Ore Estuary is vulnerable to flooding from the sea made worse by the poor condition of many of the flood defences. The proposed Flood Cell 06, Snape Maltings scheme is 1 of 4 cells identified to improve the Standard of Service of the existing flood defences and provide resilience to withstand 300mm of overtopping from a 1:200+ year event, given predicted sea levels in 2050. The Client is theEast Suffolk Water Management Board. In summary, the scope of Works for the project includes civil engineering works (but is not limited to):  Establish main site offices, compound, temporary services and access routes.  Alliance House - Installation of approximately 20m of new demountable defences along the quay side with piled and concrete slab foundation;  River Alde Quay - Installation of approximately 120m of new demountable defences along the northern quay side with piled and concrete slab foundation;  Henry Moore Lawn - Improvement to approximately 80metres of earth flood embankment to be constructed in a passive fashion to provide improved flood protection and amenity and access value around the Henry Moore Lawn area terminating at the northeastern edge of the Concert Hall building; and  Terrace Car Park - Improvement to approximately 100metres of earth flood embankment, incorporating pedestrian access provision, constructed from the River Cafe terrace area, terminating into the southeast car park area. The works are estimated to cost around £2.3million. The form of contract will be a NEC4 ECC Option A. All tender documents are available through the Client or the Client's appointed tender and contract manager Stantec UK Ltd.

  • Contract Details

    Open Contracting ID

    ocds-h6vhtk-050397

    Publication Source

    Find a Tender Service

    Procurement Stage

    TenderUpdate

    Procurement Method

    Open

    Procurement Method Details

    Below Threshold - Open Competition

    Procurement Category

    Works

    Tender Suitability

    Framework / DPS

  • Contract Classification

    CPV Code(s)

    CPV Division(s)

  • Awarding Authority

    EAST SUFFOLK WATER MANAGEMENT BOARD

    Buyer Name

    Pete Roberts

    Buyer Email

    pete.roberts@wlma.org.uk

    Buyer Phone

    07557 143072

    Buyer Address

    Pierpoint House

    King's Lynn

    PE30 5DD

    United Kingdom


Tender

Flood Cell 06, Snape Maltings

EAST SUFFOLK WATER MANAGEMENT BOARD

  • Contract Timeline

    Publication Date

    15th April 2025 18:29:04 PM

    Tender Deadline

    27th June 2025 11:00:00 AM   67 days remaining

  • Contract Summary

    The Upper Alde & Ore Estuary Embankment Improvements scheme will reduce tidal flood riskand enhance the environment in the Upper Alde and Ore Estuary. The Alde and Ore Estuary is vulnerable to flooding from the sea made worse by the poor condition of many of the flood defences. The proposed Flood Cell 06, Snape Maltings scheme is 1 of 4 cells identified to improve the Standard of Service of the existing flood defences and provide resilience to withstand 300mm of overtopping from a 1:200+ year event, given predicted sea levels in 2050. The Client is theEast Suffolk Water Management Board. In summary, the scope of Works for the project includes civil engineering works (but is not limited to):  Establish main site offices, compound, temporary services and access routes.  Alliance House - Installation of approximately 20m of new demountable defences along the quay side with piled and concrete slab foundation;  River Alde Quay - Installation of approximately 120m of new demountable defences along the northern quay side with piled and concrete slab foundation;  Henry Moore Lawn - Improvement to approximately 80metres of earth flood embankment to be constructed in a passive fashion to provide improved flood protection and amenity and access value around the Henry Moore Lawn area terminating at the northeastern edge of the Concert Hall building; and  Terrace Car Park - Improvement to approximately 100metres of earth flood embankment, incorporating pedestrian access provision, constructed from the River Cafe terrace area, terminating into the southeast car park area. The works are estimated to cost around £2.3million. The form of contract will be a NEC4 ECC Option A. All tender documents are available through the Client or the Client's appointed tender and contract manager Stantec UK Ltd.

  • Contract Details

    Open Contracting ID

    ocds-h6vhtk-050397

    Publication Source

    Find a Tender Service

    Procurement Stage

    Tender

    Procurement Method

    Open

    Procurement Method Details

    Below Threshold - Open Competition

    Procurement Category

    Works

    Tender Suitability

    Framework / DPS

  • Contract Classification

    CPV Code(s)

    CPV Division(s)

  • Awarding Authority

    EAST SUFFOLK WATER MANAGEMENT BOARD

    Buyer Name

    Pete Roberts

    Buyer Email

    pete.roberts@wlma.org.uk

    Buyer Phone

    07557 143072

    Buyer Address

    Pierpoint House

    King's Lynn

    PE30 5DD

    United Kingdom