Planning

Supply Chain Notice: BLD0366-01 Ship Hall Mega Doors

MINISTRY OF DEFENCE

  • Contract Timeline

    Publication Date

    30th June 2025 17:15:48 PM

  • Contract Summary

    Survey, Design & Installation of Ship Hall Mega Doors Building 1/122 Ship Hall B was built in 2003. The north elevation has a large opening (circa 47.1 m x 32.3 m) completed by two vertical lift fabric doors, separated by a removeable central mullion. Both doors and mullion are in a poor material condition after 20 years, and the right-hand door (viewed from external) was damaged during a storm in November 2024. The aim of this project is to replace the doors and associated equipment. The contractor shall develop a fully detailed and construction-ready design package that includes technical drawings, installation methodologies, and a comprehensive compliance plan to ensure all regulatory requirements are met. The design shall demonstrate a clear path for commissioning, testing, and integration with other systems.

  • Contract Details

    Open Contracting ID

    ocds-b5fd17-57e4cd9e-7a99-4001-8842-e5864d7a2c03

    Publication Source

    Contracts Finder

    Procurement Stage

    Planning

    Procurement Method

    N/A

    Procurement Method Details

    Procurement Category

    N/A

    Tender Suitability

    SME VCSE

    Framework / DPS

  • Contract Classification

    CPV Code(s)

    45213221

    CPV Division(s)

    45 - Construction work

  • Awarding Authority

    MINISTRY OF DEFENCE

    Buyer Name

    Buyer Email

    SCBasePersonnel@kbsmaritime.com

    Buyer Phone

    Buyer Address

    Victory Building, Portsmouth Naval Base

    Portsmouth

    PO1 3LS

    England