The Cornwall Council is seeking a contractor for the "Construction of Penzance Creative Cluster" located at Causewayhead, Penzance, TR18 2ST. This project is part of a broader initiative to regenerate Penzance's town centre, thereby enhancing local employment opportunities and community engagement. Currently at the planning stage, the procurement process adopted is an open tender, with significant key dates including an anticipated contract award in April 2021, and project completion expected by October 2022. The total contract value is approximately £4,935,186.56, and the procurement is underpinned by requirements to achieve BREEAM Excellent standards due to European Union funding regulations.

This tender presents substantial opportunities for businesses in the construction industry, particularly those experienced in complex building projects that require a high level of sustainability and compliance with regulatory standards. Suitable candidates would include general contractors with expertise in steel-frame structures, environmental certifications, and experience managing site limitations. As the project aims to create a prominent gateway into the town and supports local economic growth, businesses keen on contributing to community infrastructure development would find this an attractive opportunity.

Find more tenders on our Open Data Platform.
How relevant is this notice?

D3 Tenders Premium

Win More Public Sector Contracts

AI-powered tender discovery, pipeline management, and market intelligence — everything you need to grow your public sector business.

Notice Title

Construction of Penzance Creative Cluster, Causewayhead, Penzance, TR18 2ST

Notice Description

The proposed site is the existing Causewayhead car park in the centre of Penzance, owned by Cornwall Council with plan area for 746sqm. This scheme is part of wider strategy in Penzance to regenerate the town centre by encouraging people to live and work in the town centre, increasing footfall and spend in the main high streets. The project will support the creation of new employment and creates a prominent high-quality gateway into the town. Once the site of an historic reservoir, and later a cattle market, the site is roughly a level portion of land, with level access from Clarence Street to the north and stepped pedestrian access down onto Causewayhead. There is restricted space for construction activities and material storage which will impact construction. The structural solution comprises small piles, foundations and ground beams. The width of the reservoir is such that the building cannot span clear over it without increasing the depth of the structure significantly. The external stone/brick walling to the site is largely retained with minimal disruption, particularly to the lower, older levels. The structure is steel frame and uses concrete hollow planks to form the decks. External walls are largely framed with SFS and clad with Pilkington 'Profilit' glazing or Veio Zinc standing seam cladding. Painted hot rolled metal sections 'edge' the top and bottom of the West block. Internal walls will mostly comprise lightweight dry-lined partitions with fare-faced block walls to plant areas. The pitched roofs are Veio Zinc standing seam the flat roof areas are Bauder on insulation laid to falls. Cornwall Council have appointed a specialist design team, project management and cost consultancy services to deliver the developed design of the project and submit all consents and start contractor engagement. The project is currently at the end of RIBA Stage 4 and is co-funded by ERDF (Match Funding); as a result, the contractor will need to comply with all related requirements and guidance in delivery of an ERDF project including branding requirements. Conditional Planning Permission has been granted by Cornwall Council under PA20/02440, and it is anticipated that at least some of these conditions will be passed to the contractor for discharge. The contractor will also be responsible for obtaining the targeted BREEAM Credits available during RIBA Stages 5-7 inclusive. All projects funded through ERDF must achieve BREEAM Excellent. The contractor will be responsible for obtaining each of the BREEAM credits targeted during RIBA Stages 5 and 6 and will also be responsible for discharging each of the outstanding planning conditions listed within the works information. The Council anticipates the Contract Award to take place during April 2021, with completion and occupation of the new facilities during October 2022. This tender seeks to secure a contractor to deliver the required construction works, as outline above and detailed within the works information. Project Reference DN513773

Lot Information

Lot 1

The structural solution comprises small piles, foundations and ground beams. The width of the reservoir is such that the building cannot span clear over it without increasing the depth of the structure significantly. The external stone/brick walling to the site is largely retained with minimal disruption, particularly to the lower, older levels. The structure is steel frame and uses concrete hollow planks to form the decks. External walls are largely framed with SFS and clad with Pilkington 'Profilit' glazing or Veio Zinc standing seam cladding. Painted hot rolled metal sections 'edge' the top and bottom of the West block. Internal walls will mostly comprise lightweight dry-lined partitions with fare-faced block walls to plant areas. The pitched roofs are Veio Zinc standing seam the flat roof areas are Bauder on insulation laid to falls. The project is currently at the end of RIBA Stage 4 and is co-funded by ERDF (Match Funding); as a result, the contractor will need to comply with all related requirements and guidance in delivery of an ERDF project including branding requirements. Conditional Planning Permission has been granted by Cornwall Council under PA20/02440, and it is anticipated that at least some of these conditions will be passed to the contractor for discharge. The contractor will also be responsible for obtaining the targeted BREEAM Credits available during RIBA Stages 5-7 inclusive. All projects funded through ERDF must achieve BREEAM Excellent. The contractor will be responsible for obtaining each of the BREEAM credits targeted during RIBA Stages 5 and 6 and will also be responsible for discharging each of the outstanding planning conditions

Publication & Lifecycle

Open Contracting ID
ocds-h6vhtk-02bf64
Publication Source
Find A Tender Service
Latest Notice
https://www.find-tender.service.gov.uk/Notice/014321-2021
Current Stage
Award
All Stages
Award

Procurement Classification

Notice Type
Award Notice
Procurement Type
Standard
Procurement Category
Works
Procurement Method
Open
Procurement Method Details
Open procedure
Tender Suitability
Not specified
Awardee Scale
Large

Common Procurement Vocabulary (CPV)

CPV Divisions

45 - Construction work


CPV Codes

45000000 - Construction work

Notice Value(s)

Tender Value
Not specified
Lots Value
Not specified
Awards Value
Not specified
Contracts Value
£4,935,186 £1M-£10M

Notice Dates

Publication Date
23 Jun 20214 years ago
Submission Deadline
Not specified
Future Notice Date
Not specified
Award Date
24 May 20214 years ago
Contract Period
Not specified - Not specified
Recurrence
Not specified

Notice Status

Tender Status
Complete
Lots Status
Cancelled
Awards Status
Active
Contracts Status
Active

Contracting Authority (Buyer)

Main Buyer
CORNWALL COUNCIL
Additional Buyers

EUROPEAN UNION

Contact Name
Mr James Howarth
Contact Email
james.howarth@cornwall.gov.uk
Contact Phone
Not specified

Buyer Location

Locality
TRURO
Postcode
TR1 3AY
Post Town
Truro
Country
England

Major Region (ITL 1)
TLK South West (England)
Basic Region (ITL 2)
TLK3 Cornwall and Isles of Scilly
Small Region (ITL 3)
TLK30 Cornwall and Isles of Scilly
Delivery Location
TLK3 Cornwall and Isles of Scilly

Local Authority
Cornwall
Electoral Ward
Truro Boscawen & Redannick
Westminster Constituency
Truro and Falmouth

Supplier Information

Number of Suppliers
1
Supplier Name

MIDAS CONSTRUCTION

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

Download

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

{
    "tag": [
        "compiled"
    ],
    "id": "ocds-h6vhtk-02bf64-2021-06-23T14:41:45+01:00",
    "date": "2021-06-23T14:41:45+01:00",
    "ocid": "ocds-h6vhtk-02bf64",
    "initiationType": "tender",
    "tender": {
        "id": "DN513773",
        "legalBasis": {
            "id": "32014L0024",
            "scheme": "CELEX"
        },
        "title": "Construction of Penzance Creative Cluster, Causewayhead, Penzance, TR18 2ST",
        "status": "complete",
        "classification": {
            "scheme": "CPV",
            "id": "45000000",
            "description": "Construction work"
        },
        "mainProcurementCategory": "works",
        "description": "The proposed site is the existing Causewayhead car park in the centre of Penzance, owned by Cornwall Council with plan area for 746sqm. This scheme is part of wider strategy in Penzance to regenerate the town centre by encouraging people to live and work in the town centre, increasing footfall and spend in the main high streets. The project will support the creation of new employment and creates a prominent high-quality gateway into the town. Once the site of an historic reservoir, and later a cattle market, the site is roughly a level portion of land, with level access from Clarence Street to the north and stepped pedestrian access down onto Causewayhead. There is restricted space for construction activities and material storage which will impact construction. The structural solution comprises small piles, foundations and ground beams. The width of the reservoir is such that the building cannot span clear over it without increasing the depth of the structure significantly. The external stone/brick walling to the site is largely retained with minimal disruption, particularly to the lower, older levels. The structure is steel frame and uses concrete hollow planks to form the decks. External walls are largely framed with SFS and clad with Pilkington 'Profilit' glazing or Veio Zinc standing seam cladding. Painted hot rolled metal sections 'edge' the top and bottom of the West block. Internal walls will mostly comprise lightweight dry-lined partitions with fare-faced block walls to plant areas. The pitched roofs are Veio Zinc standing seam the flat roof areas are Bauder on insulation laid to falls. Cornwall Council have appointed a specialist design team, project management and cost consultancy services to deliver the developed design of the project and submit all consents and start contractor engagement. The project is currently at the end of RIBA Stage 4 and is co-funded by ERDF (Match Funding); as a result, the contractor will need to comply with all related requirements and guidance in delivery of an ERDF project including branding requirements. Conditional Planning Permission has been granted by Cornwall Council under PA20/02440, and it is anticipated that at least some of these conditions will be passed to the contractor for discharge. The contractor will also be responsible for obtaining the targeted BREEAM Credits available during RIBA Stages 5-7 inclusive. All projects funded through ERDF must achieve BREEAM Excellent. The contractor will be responsible for obtaining each of the BREEAM credits targeted during RIBA Stages 5 and 6 and will also be responsible for discharging each of the outstanding planning conditions listed within the works information. The Council anticipates the Contract Award to take place during April 2021, with completion and occupation of the new facilities during October 2022. This tender seeks to secure a contractor to deliver the required construction works, as outline above and detailed within the works information. Project Reference DN513773",
        "lots": [
            {
                "id": "1",
                "description": "The structural solution comprises small piles, foundations and ground beams. The width of the reservoir is such that the building cannot span clear over it without increasing the depth of the structure significantly. The external stone/brick walling to the site is largely retained with minimal disruption, particularly to the lower, older levels. The structure is steel frame and uses concrete hollow planks to form the decks. External walls are largely framed with SFS and clad with Pilkington 'Profilit' glazing or Veio Zinc standing seam cladding. Painted hot rolled metal sections 'edge' the top and bottom of the West block. Internal walls will mostly comprise lightweight dry-lined partitions with fare-faced block walls to plant areas. The pitched roofs are Veio Zinc standing seam the flat roof areas are Bauder on insulation laid to falls. The project is currently at the end of RIBA Stage 4 and is co-funded by ERDF (Match Funding); as a result, the contractor will need to comply with all related requirements and guidance in delivery of an ERDF project including branding requirements. Conditional Planning Permission has been granted by Cornwall Council under PA20/02440, and it is anticipated that at least some of these conditions will be passed to the contractor for discharge. The contractor will also be responsible for obtaining the targeted BREEAM Credits available during RIBA Stages 5-7 inclusive. All projects funded through ERDF must achieve BREEAM Excellent. The contractor will be responsible for obtaining each of the BREEAM credits targeted during RIBA Stages 5 and 6 and will also be responsible for discharging each of the outstanding planning conditions",
                "awardCriteria": {
                    "criteria": [
                        {
                            "name": "Quality",
                            "type": "quality",
                            "description": "30"
                        },
                        {
                            "type": "price",
                            "description": "70"
                        }
                    ]
                },
                "hasOptions": false,
                "status": "cancelled"
            }
        ],
        "items": [
            {
                "id": "1",
                "deliveryAddresses": [
                    {
                        "region": "UKK3"
                    }
                ],
                "relatedLot": "1"
            }
        ],
        "procurementMethod": "open",
        "procurementMethodDetails": "Open procedure"
    },
    "awards": [
        {
            "id": "014321-2021-DN513773-1",
            "relatedLots": [
                "1"
            ],
            "status": "active",
            "suppliers": [
                {
                    "id": "GB-FTS-20358",
                    "name": "Midas Construction Limited"
                }
            ]
        }
    ],
    "parties": [
        {
            "id": "GB-FTS-215",
            "name": "Cornwall Council",
            "identifier": {
                "legalName": "Cornwall Council"
            },
            "address": {
                "streetAddress": "County Hall, Treyew Road",
                "locality": "Truro",
                "region": "UKK3",
                "postalCode": "TR1 3AY",
                "countryName": "United Kingdom"
            },
            "contactPoint": {
                "name": "Mr James Howarth",
                "email": "james.howarth@cornwall.gov.uk"
            },
            "roles": [
                "buyer"
            ],
            "details": {
                "url": "http://www.cornwall.gov.uk",
                "classifications": [
                    {
                        "scheme": "TED_CA_TYPE",
                        "id": "REGIONAL_AUTHORITY",
                        "description": "Regional or local authority"
                    },
                    {
                        "scheme": "COFOG",
                        "id": "01",
                        "description": "General public services"
                    }
                ]
            }
        },
        {
            "id": "GB-FTS-172",
            "name": "European Union",
            "roles": [
                "funder"
            ]
        },
        {
            "id": "GB-FTS-20358",
            "name": "Midas Construction Limited",
            "identifier": {
                "legalName": "Midas Construction Limited"
            },
            "address": {
                "locality": "Exeter",
                "region": "UKK4",
                "countryName": "United Kingdom"
            },
            "roles": [
                "supplier"
            ],
            "details": {
                "scale": "large"
            }
        },
        {
            "id": "GB-FTS-20355",
            "name": "Cornwall Council Monitoring Officer",
            "identifier": {
                "legalName": "Cornwall Council Monitoring Officer"
            },
            "address": {
                "locality": "Truro",
                "countryName": "United Kingdom"
            },
            "roles": [
                "reviewBody"
            ]
        }
    ],
    "buyer": {
        "id": "GB-FTS-215",
        "name": "Cornwall Council"
    },
    "planning": {
        "budget": {
            "finance": [
                {
                    "id": "1",
                    "description": "Penzance Creative Cluster",
                    "financingParty": {
                        "name": "European Union",
                        "id": "GB-FTS-172"
                    },
                    "relatedLots": [
                        "1"
                    ]
                }
            ]
        }
    },
    "contracts": [
        {
            "id": "014321-2021-DN513773-1",
            "awardID": "014321-2021-DN513773-1",
            "status": "active",
            "value": {
                "amount": 4935186.56,
                "currency": "GBP"
            },
            "dateSigned": "2021-05-25T00:00:00+01:00"
        }
    ],
    "bids": {
        "statistics": [
            {
                "id": "1",
                "measure": "bids",
                "relatedLot": "1",
                "value": 1
            },
            {
                "id": "2",
                "measure": "smeBids",
                "relatedLot": "1",
                "value": 0
            },
            {
                "id": "3",
                "measure": "foreignBidsFromEU",
                "relatedLot": "1",
                "value": 0
            },
            {
                "id": "4",
                "measure": "foreignBidsFromNonEU",
                "relatedLot": "1",
                "value": 1
            },
            {
                "id": "5",
                "measure": "electronicBids",
                "relatedLot": "1",
                "value": 1
            }
        ]
    },
    "links": [
        {
            "rel": "prev",
            "href": "https://ted.europa.eu/udl?uri=TED:NOTICE:026453-2021:TEXT:EN:HTML"
        }
    ],
    "language": "en"
}