The procurement process involves the appointment of an Integrated Supply Team (IST) for the construction of the new Post-Primary School at New-Bridge Integrated College, located in Loughbrickland, UK. The process is governed by the Public Contracts Regulations 2015 and has reached the award stage, with the contract awarded on 26th November 2021. The value of the contract is approximately £20.6 million and it is expected to be carried out over a 30-month construction period. The tender follows a selective procurement method and falls under the industry category of works, specifically focusing on electrical installation work and construction for school buildings.

This tender presents significant opportunities for businesses involved in construction and educational infrastructure, particularly firms that specialise in electrical installations, mechanical engineering works, and large-scale building projects. The phased development approach allows businesses to showcase their capacity to manage complex projects while maintaining operational facilities. Companies experienced in similar environments, particularly those large enough to handle significant contracts, such as this one, would find this opportunity favourable for growth and expansion in the public sector.

Find more tenders on our Open Data Platform.
How relevant is this notice?

D3 Tenders Premium

Win More Public Sector Contracts

AI-powered tender discovery, pipeline management, and market intelligence — everything you need to grow your public sector business.

Notice Title

DE2957529 Appointment of an IST for New-Bridge Integrated College Loughbrickland

Notice Description

The project is for the design, supply, delivery, receiving, off-loading, setting into position, fixing, erection, building testing, commissioning and finishing in every respect of the new Post-Primary School for 670 pupils to include external hard play, synthetic and grass pitches, tennis courts, Sports Hall, School Meals Accommodation, car and bus parking and drop-off and a new entrance onto Donard View Road. The design has been completed to RIBA Stage 3. The successful IST will be responsible for completing RIBA Stage 4 onwards. It is proposed to construct the new school on the existing site with the grass pitches being developed on a newly purchased site adjacent to the existing. There are no established site services on the additional site. The main school building will be located on the middle portion of the site slightly further back on the site than the current main building of the School. It is anticipated that extensive phasing will be required with the school remaining fully operational during the construction period. By facilitating a phased development, a portion of the new school buildings are constructed on part of the footprint of the existing school buildings. This allows for a more efficient use of the site with no diversion of the mains sewer necessary. The estimated programme for the construction period is of the order of 30 months (overall incl pre-construction is 35 months approx). Full details will be provided in the ITT documentation.

Lot Information

Lot 1

The project is for the design, supply, delivery, receiving, off-loading, setting into position, fixing, erection, building testing, commissioning and finishing in every respect of the new Post-Primary School for 670 pupils to include external hard play, synthetic and grass pitches, tennis courts, Sports Hall, School Meals Accommodation, car and bus parking and drop-off and a new entrance onto Donard View Road. The design has been completed to RIBA Stage 3. The successful IST will be responsible for completing RIBA Stage 4 onwards. It is proposed to construct the new school on the existing site with the grass pitches being developed on a newly purchased site adjacent to the existing. There are no established site services on the additional site. The main school building will be located on the middle portion of the site slightly further back on the site than the current main building of the School. It is anticipated that extensive phasing will be required with the school remaining fully operational during the construction period. By facilitating a phased development, a portion of the new school buildings are constructed on part of the footprint of the existing school buildings. This allows for a more efficient use of the site with no diversion of the mains sewer necessary. The estimated programme for the construction period is of the order of 30 months (overall incl pre-construction is 35 months approx). Full details will be provided in the ITT documentation.

Publication & Lifecycle

Open Contracting ID
ocds-h6vhtk-02fe83
Publication Source
Find A Tender Service
Latest Notice
https://www.find-tender.service.gov.uk/Notice/030476-2021
Current Stage
Award
All Stages
Award

Procurement Classification

Notice Type
Award Notice
Procurement Type
Standard
Procurement Category
Works
Procurement Method
Selective
Procurement Method Details
Restricted procedure
Tender Suitability
Not specified
Awardee Scale
Large

Common Procurement Vocabulary (CPV)

CPV Divisions

45 - Construction work


CPV Codes

45210000 - Building construction work

45214200 - Construction work for school buildings

45214220 - Secondary school construction work

45310000 - Electrical installation work

45351000 - Mechanical engineering installation works

Notice Value(s)

Tender Value
Not specified
Lots Value
Not specified
Awards Value
Not specified
Contracts Value
£20,599,220 £10M-£100M

Notice Dates

Publication Date
8 Dec 20214 years ago
Submission Deadline
Not specified
Future Notice Date
Not specified
Award Date
26 Nov 20214 years ago
Contract Period
Not specified - Not specified
Recurrence
Not specified

Notice Status

Tender Status
Complete
Lots Status
Cancelled
Awards Status
Active
Contracts Status
Active

Contracting Authority (Buyer)

Main Buyer
THE TRUSTEES OF NEW-BRIDGE INTEGRATED COLLEGE
Contact Name
Construct.Info
Contact Email
construct.info@finance-ni.gov.uk
Contact Phone
+44 2890816555

Buyer Location

Locality
BANBRIDGE
Postcode
BT32 3LN
Post Town
Northern Ireland
Country
Northern Ireland

Major Region (ITL 1)
TLN Northern Ireland
Basic Region (ITL 2)
TLN0 Northern Ireland
Small Region (ITL 3)
TLN07 Armagh City, Banbridge and Craigavon
Delivery Location
TLN0 Northern Ireland

Local Authority
Armagh City, Banbridge and Craigavon
Electoral Ward
Loughbrickland
Westminster Constituency
South Down

Supplier Information

Number of Suppliers
1
Supplier Name

GANSON

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

Download

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

{
    "tag": [
        "compiled"
    ],
    "id": "ocds-h6vhtk-02fe83-2021-12-08T10:25:02Z",
    "date": "2021-12-08T10:25:02Z",
    "ocid": "ocds-h6vhtk-02fe83",
    "initiationType": "tender",
    "tender": {
        "id": "ocds-h6vhtk-02fe83",
        "legalBasis": {
            "id": "32014L0024",
            "scheme": "CELEX"
        },
        "title": "DE2957529 Appointment of an IST for New-Bridge Integrated College Loughbrickland",
        "status": "complete",
        "classification": {
            "scheme": "CPV",
            "id": "45310000",
            "description": "Electrical installation work"
        },
        "mainProcurementCategory": "works",
        "description": "The project is for the design, supply, delivery, receiving, off-loading, setting into position, fixing, erection, building testing, commissioning and finishing in every respect of the new Post-Primary School for 670 pupils to include external hard play, synthetic and grass pitches, tennis courts, Sports Hall, School Meals Accommodation, car and bus parking and drop-off and a new entrance onto Donard View Road. The design has been completed to RIBA Stage 3. The successful IST will be responsible for completing RIBA Stage 4 onwards. It is proposed to construct the new school on the existing site with the grass pitches being developed on a newly purchased site adjacent to the existing. There are no established site services on the additional site. The main school building will be located on the middle portion of the site slightly further back on the site than the current main building of the School. It is anticipated that extensive phasing will be required with the school remaining fully operational during the construction period. By facilitating a phased development, a portion of the new school buildings are constructed on part of the footprint of the existing school buildings. This allows for a more efficient use of the site with no diversion of the mains sewer necessary. The estimated programme for the construction period is of the order of 30 months (overall incl pre-construction is 35 months approx). Full details will be provided in the ITT documentation.",
        "lots": [
            {
                "id": "1",
                "description": "The project is for the design, supply, delivery, receiving, off-loading, setting into position, fixing, erection, building testing, commissioning and finishing in every respect of the new Post-Primary School for 670 pupils to include external hard play, synthetic and grass pitches, tennis courts, Sports Hall, School Meals Accommodation, car and bus parking and drop-off and a new entrance onto Donard View Road. The design has been completed to RIBA Stage 3. The successful IST will be responsible for completing RIBA Stage 4 onwards. It is proposed to construct the new school on the existing site with the grass pitches being developed on a newly purchased site adjacent to the existing. There are no established site services on the additional site. The main school building will be located on the middle portion of the site slightly further back on the site than the current main building of the School. It is anticipated that extensive phasing will be required with the school remaining fully operational during the construction period. By facilitating a phased development, a portion of the new school buildings are constructed on part of the footprint of the existing school buildings. This allows for a more efficient use of the site with no diversion of the mains sewer necessary. The estimated programme for the construction period is of the order of 30 months (overall incl pre-construction is 35 months approx). Full details will be provided in the ITT documentation.",
                "awardCriteria": {
                    "criteria": [
                        {
                            "name": "QUALITY",
                            "type": "quality",
                            "description": "45"
                        },
                        {
                            "name": "PRICE",
                            "type": "cost",
                            "description": "55"
                        }
                    ]
                },
                "hasOptions": false,
                "status": "cancelled"
            }
        ],
        "items": [
            {
                "id": "1",
                "additionalClassifications": [
                    {
                        "scheme": "CPV",
                        "id": "45214200",
                        "description": "Construction work for school buildings"
                    },
                    {
                        "scheme": "CPV",
                        "id": "45214220",
                        "description": "Secondary school construction work"
                    },
                    {
                        "scheme": "CPV",
                        "id": "45210000",
                        "description": "Building construction work"
                    },
                    {
                        "scheme": "CPV",
                        "id": "45351000",
                        "description": "Mechanical engineering installation works"
                    }
                ],
                "deliveryAddresses": [
                    {
                        "region": "UKN0"
                    }
                ],
                "relatedLot": "1"
            }
        ],
        "procurementMethod": "selective",
        "procurementMethodDetails": "Restricted procedure",
        "coveredBy": [
            "GPA"
        ],
        "reviewDetails": "This procurement is governed by the Public Contracts Regulations 2015 and. provides for economic operators who have suffered or who risk suffering loss or damage as a consequence of an alleged breach of the. duty owed in accordance with Regulation 91 to start proceedings in the High Court.. . A standstill period will commence at the point. information on the award of the contract is communicated to tenderers. That notification will provide information on the award decision.. The standstill period, which will be for a minimum of 10 calendar days, provides time for unsuccessful tenderers to challenge the award. decision before the contract is entered into.. . Any proceedings relating to any perceived non-compliance with the relevant law must be. started within 30 days, beginning with the date when the economic operator first knew, or ought to have known that grounds for starting. the proceedings had arisen. (A court may extend the time limit to 3 months, where the court considers that there is a good reason for. doing so).."
    },
    "awards": [
        {
            "id": "030476-2021-1-1",
            "relatedLots": [
                "1"
            ],
            "title": "Contract",
            "status": "active",
            "suppliers": [
                {
                    "id": "GB-FTS-37081",
                    "name": "GANSON UK LTD"
                }
            ]
        }
    ],
    "parties": [
        {
            "id": "GB-FTS-37080",
            "name": "The Trustees of New-Bridge Integrated College",
            "identifier": {
                "legalName": "The Trustees of New-Bridge Integrated College"
            },
            "address": {
                "streetAddress": "25 Donard View Rd, Loughbrickland",
                "locality": "Banbridge",
                "region": "UK",
                "postalCode": "BT32 3LN",
                "countryName": "United Kingdom"
            },
            "contactPoint": {
                "name": "Construct.Info",
                "telephone": "+44 2890816555",
                "email": "Construct.Info@finance-ni.gov.uk"
            },
            "roles": [
                "buyer",
                "centralPurchasingBody"
            ],
            "details": {
                "url": "https://etendersni.gov.uk/epps",
                "buyerProfile": "https://etendersni.gov.uk/epps",
                "classifications": [
                    {
                        "scheme": "TED_CA_TYPE",
                        "id": "BODY_PUBLIC",
                        "description": "Body governed by public law"
                    },
                    {
                        "scheme": "COFOG",
                        "id": "09",
                        "description": "Education"
                    }
                ]
            }
        },
        {
            "id": "GB-FTS-37081",
            "name": "GANSON UK LTD",
            "identifier": {
                "legalName": "GANSON UK LTD"
            },
            "address": {
                "streetAddress": "Clarmont Avenue",
                "locality": "Newry",
                "region": "UK",
                "postalCode": "BT31 9BX",
                "countryName": "United Kingdom"
            },
            "contactPoint": {
                "email": "gerard@gansonuk.co.uk"
            },
            "roles": [
                "supplier"
            ],
            "details": {
                "url": "https://etendersni.gov.uk/epps",
                "scale": "large"
            }
        },
        {
            "id": "GB-FTS-37082",
            "name": "Department of Finance, Construction Procurement Delivery Procurement Operations Branch",
            "identifier": {
                "legalName": "Department of Finance, Construction Procurement Delivery Procurement Operations Branch"
            },
            "address": {
                "locality": "Belfast",
                "countryName": "United Kingdom"
            },
            "roles": [
                "reviewBody"
            ]
        }
    ],
    "buyer": {
        "id": "GB-FTS-37080",
        "name": "The Trustees of New-Bridge Integrated College"
    },
    "contracts": [
        {
            "id": "030476-2021-1-1",
            "awardID": "030476-2021-1-1",
            "title": "Contract",
            "status": "active",
            "value": {
                "amount": 20599220,
                "currency": "GBP"
            },
            "dateSigned": "2021-11-26T00:00:00Z"
        }
    ],
    "bids": {
        "statistics": [
            {
                "id": "1",
                "measure": "bids",
                "relatedLot": "1",
                "value": 8
            },
            {
                "id": "2",
                "measure": "smeBids",
                "relatedLot": "1",
                "value": 1
            },
            {
                "id": "3",
                "measure": "foreignBidsFromEU",
                "relatedLot": "1",
                "value": 0
            },
            {
                "id": "4",
                "measure": "foreignBidsFromNonEU",
                "relatedLot": "1",
                "value": 1
            },
            {
                "id": "5",
                "measure": "electronicBids",
                "relatedLot": "1",
                "value": 8
            }
        ]
    },
    "links": [
        {
            "rel": "prev",
            "href": "https://ted.europa.eu/udl?uri=TED:NOTICE:320302-2020:TEXT:EN:HTML"
        }
    ],
    "language": "en"
}