Notice Information
Notice Title
HR Transformation Programme
Notice Description
This is a VEAT notice to show our intention to award a contract to Anchorstone Consulting for the delivery of the remaining elements of Coventry University Group's HR Transformation Programme, including the design, build, test and implementation of SuccessFactors modules and embedding the business change across the organisation.
Lot Information
Lot 1
Following the departure, by mutual agreement, of PA Consulting who were originally awarded the contract to deliver the HR transformational change at Coventry University Group, there is now an immediate need to progress at pace the remaining elements of the Programme with Anchorstone Consulting staff in order to protect the Programme's set objectives and anticipated benefits. Consultancy services from Anchorstone Consulting have previously been procured to support the Business Change and readiness deliverables, Anchorstone resource have also been involved in the recent technical design handover from PA Consulting due to the need for specific SuccessFactors Consultancy expertise. They have reviewed and validated the solution design work undertaken so far to ensure the Programme requirements have been met. Anchorstone Consultuing also have a clear understanding of the detailed activities required to fully implement the Programme. CUG is now at a critical stage of delivery with the target date of delivering Employee Central, Payroll, ASK HR and SAP JAM for May 2022 followed quickly by Phase 2 deliverables (Learning, Succession, Talent, Performance and Compensation.) The Programme is in the middle of User Acceptance Testing and about to embark on Parallel Payroll running. From an efficiency and effectiveness perspective it would be beneficial for CUG to seek to extend the resource profile from Anchorstone Consulting to deliver the remaining elements of the Programme, this is due to their in-depth knowledge already gained. Any delay in pausing this Programme in order to go through a full procurement process would be detrimental to Coventry University Group, as this would result in further delay in the delivery of the Programme, resulting in additional costs being incurred, there is also a significant risk of losing internal staff and knowledge gained already on the Programme. SuccessFactors Modules to be fully designed, built, tested and Implemented in two phases: Phase 1: Employee Central, Payroll, Recruitment, Onboarding ASK HR, SAP JAM, Reporting. Target date is April/May 2022. Phase 2: Performance and Goal Management, Succession & Development, Learning, Compensation. Target date is July/August 2022. Note: Workforce Analytics and Qualtrics are expected to be designed, built and tested by our current software Partner NTT.
Procurement Information
Following the departure, by mutual agreement, of PA Consulting who were originally awarded the contract to deliver the HR transformational change at Coventry University Group, there is now an immediate need to progress at pace the remaining elements of the Programme with Anchorstone Consulting staff in order to protect the Programme's set objectives and anticipated benefits. Consultancy services from Anchorstone Consulting have previously been procured to support the Business Change and readiness deliverables, Anchorstone resource have also been involved in the recent technical design handover from PA Consulting due to the need for specific SuccessFactors Consultancy expertise. They have reviewed and validated the solution design work undertaken so far to ensure the Programme requirements have been met. Anchorstone Consultuing also have a clear understanding of the detailed activities required to fully implement the Programme. CUG is now at a critical stage of delivery with the target date of delivering Employee Central, Payroll, ASK HR and SAP JAM for May 2022 followed quickly by Phase 2 deliverables (Learning, Succession, Talent, Performance and Compensation.) The Programme is in the middle of User Acceptance Testing and about to embark on Parallel Payroll running. From an efficiency and effectiveness perspective it would be beneficial for CUG to seek to extend the resource profile from Anchorstone Consulting to deliver the remaining elements of the Programme, this is due to their in-depth knowledge already gained. Any delay in pausing this Programme in order to go through a full procurement process would be detrimental to Coventry University Group, as this would result in further delay in the delivery of the Programme, resulting in additional costs being incurred, there is also a significant risk of losing internal staff and knowledge gained already on the Programme. SuccessFactors Modules to be fully designed, built, tested and Implemented in two phases: Phase 1: Employee Central, Payroll, Recruitment, Onboarding ASK HR, SAP JAM, Reporting. Target date is April/May 2022. Phase 2: Performance and Goal Management, Succession & Development, Learning, Compensation. Target date is July/August 2022. Note: Workforce Analytics and Qualtrics are expected to be designed, built and tested by our current software Partner NTT.
Notice Details
Publication & Lifecycle
- Open Contracting ID
- ocds-h6vhtk-031142
- Publication Source
- Find A Tender Service
- Latest Notice
- https://www.find-tender.service.gov.uk/Notice/003103-2022
- Current Stage
- Award
- All Stages
- Tender, Award
Procurement Classification
- Notice Type
- Tender Notice
- Procurement Type
- Standard
- Procurement Category
- Services
- Procurement Method
- Limited
- Procurement Method Details
- Award procedure without prior publication of a call for competition
- Tender Suitability
- Not specified
- Awardee Scale
- Large
Common Procurement Vocabulary (CPV)
- CPV Divisions
79 - Business services: law, marketing, consulting, recruitment, printing and security
-
- CPV Codes
79410000 - Business and management consultancy services
Notice Value(s)
- Tender Value
- Not specified
- Lots Value
- Not specified
- Awards Value
- Not specified
- Contracts Value
- £1,307,280 £1M-£10M
Notice Dates
- Publication Date
- 3 Feb 20224 years ago
- Submission Deadline
- Not specified
- Future Notice Date
- Not specified
- Award Date
- 31 Jan 20224 years ago
- Contract Period
- Not specified - Not specified
- Recurrence
- Not specified
Notice Status
- Tender Status
- Complete
- Lots Status
- Not Specified
- Awards Status
- Active
- Contracts Status
- Active
Buyer & Supplier
Contracting Authority (Buyer)
- Main Buyer
- COVENTRY UNIVERSITY
- Contact Name
- Not specified
- Contact Email
- ad7164@coventry.ac.uk
- Contact Phone
- Not specified
Buyer Location
- Locality
- COVENTRY
- Postcode
- CV1 5FB
- Post Town
- Coventry
- Country
- England
-
- Major Region (ITL 1)
- TLG West Midlands (England)
- Basic Region (ITL 2)
- TLG3 West Midlands
- Small Region (ITL 3)
- TLG33 Coventry
- Delivery Location
- TLG3 West Midlands
-
- Local Authority
- Coventry
- Electoral Ward
- St Michael's
- Westminster Constituency
- Coventry South
Further Information
Notice URLs
Open Contracting Data Standard (OCDS)
View full OCDS Record for this contracting process
The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.
{
"tag": [
"compiled"
],
"id": "ocds-h6vhtk-031142-2022-02-03T09:26:27Z",
"date": "2022-02-03T09:26:27Z",
"ocid": "ocds-h6vhtk-031142",
"initiationType": "tender",
"tender": {
"id": "ocds-h6vhtk-031142",
"legalBasis": {
"id": "32014L0024",
"scheme": "CELEX"
},
"title": "HR Transformation Programme",
"status": "complete",
"classification": {
"scheme": "CPV",
"id": "79410000",
"description": "Business and management consultancy services"
},
"mainProcurementCategory": "services",
"description": "This is a VEAT notice to show our intention to award a contract to Anchorstone Consulting for the delivery of the remaining elements of Coventry University Group's HR Transformation Programme, including the design, build, test and implementation of SuccessFactors modules and embedding the business change across the organisation.",
"lots": [
{
"id": "1",
"description": "Following the departure, by mutual agreement, of PA Consulting who were originally awarded the contract to deliver the HR transformational change at Coventry University Group, there is now an immediate need to progress at pace the remaining elements of the Programme with Anchorstone Consulting staff in order to protect the Programme's set objectives and anticipated benefits. Consultancy services from Anchorstone Consulting have previously been procured to support the Business Change and readiness deliverables, Anchorstone resource have also been involved in the recent technical design handover from PA Consulting due to the need for specific SuccessFactors Consultancy expertise. They have reviewed and validated the solution design work undertaken so far to ensure the Programme requirements have been met. Anchorstone Consultuing also have a clear understanding of the detailed activities required to fully implement the Programme. CUG is now at a critical stage of delivery with the target date of delivering Employee Central, Payroll, ASK HR and SAP JAM for May 2022 followed quickly by Phase 2 deliverables (Learning, Succession, Talent, Performance and Compensation.) The Programme is in the middle of User Acceptance Testing and about to embark on Parallel Payroll running. From an efficiency and effectiveness perspective it would be beneficial for CUG to seek to extend the resource profile from Anchorstone Consulting to deliver the remaining elements of the Programme, this is due to their in-depth knowledge already gained. Any delay in pausing this Programme in order to go through a full procurement process would be detrimental to Coventry University Group, as this would result in further delay in the delivery of the Programme, resulting in additional costs being incurred, there is also a significant risk of losing internal staff and knowledge gained already on the Programme. SuccessFactors Modules to be fully designed, built, tested and Implemented in two phases: Phase 1: Employee Central, Payroll, Recruitment, Onboarding ASK HR, SAP JAM, Reporting. Target date is April/May 2022. Phase 2: Performance and Goal Management, Succession & Development, Learning, Compensation. Target date is July/August 2022. Note: Workforce Analytics and Qualtrics are expected to be designed, built and tested by our current software Partner NTT.",
"hasOptions": false
}
],
"items": [
{
"id": "1",
"deliveryAddresses": [
{
"region": "UKG3"
}
],
"relatedLot": "1"
}
],
"procurementMethod": "limited",
"procurementMethodDetails": "Award procedure without prior publication of a call for competition",
"procurementMethodRationaleClassifications": [
{
"scheme": "TED_PT_AWARD_CONTRACT_WITHOUT_CALL",
"id": "D_OUTSIDE_SCOPE",
"description": "The procurement falls outside the scope of application of the directive"
}
],
"procurementMethodRationale": "Following the departure, by mutual agreement, of PA Consulting who were originally awarded the contract to deliver the HR transformational change at Coventry University Group, there is now an immediate need to progress at pace the remaining elements of the Programme with Anchorstone Consulting staff in order to protect the Programme's set objectives and anticipated benefits. Consultancy services from Anchorstone Consulting have previously been procured to support the Business Change and readiness deliverables, Anchorstone resource have also been involved in the recent technical design handover from PA Consulting due to the need for specific SuccessFactors Consultancy expertise. They have reviewed and validated the solution design work undertaken so far to ensure the Programme requirements have been met. Anchorstone Consultuing also have a clear understanding of the detailed activities required to fully implement the Programme. CUG is now at a critical stage of delivery with the target date of delivering Employee Central, Payroll, ASK HR and SAP JAM for May 2022 followed quickly by Phase 2 deliverables (Learning, Succession, Talent, Performance and Compensation.) The Programme is in the middle of User Acceptance Testing and about to embark on Parallel Payroll running. From an efficiency and effectiveness perspective it would be beneficial for CUG to seek to extend the resource profile from Anchorstone Consulting to deliver the remaining elements of the Programme, this is due to their in-depth knowledge already gained. Any delay in pausing this Programme in order to go through a full procurement process would be detrimental to Coventry University Group, as this would result in further delay in the delivery of the Programme, resulting in additional costs being incurred, there is also a significant risk of losing internal staff and knowledge gained already on the Programme. SuccessFactors Modules to be fully designed, built, tested and Implemented in two phases: Phase 1: Employee Central, Payroll, Recruitment, Onboarding ASK HR, SAP JAM, Reporting. Target date is April/May 2022. Phase 2: Performance and Goal Management, Succession & Development, Learning, Compensation. Target date is July/August 2022. Note: Workforce Analytics and Qualtrics are expected to be designed, built and tested by our current software Partner NTT.",
"amendments": [
{
"id": "1",
"unstructuredChanges": [
{
"newValue": {
"text": "Following the previous procurement of HR consultancy services on or around 2019, there is now an immediate need to progress at pace the remaining elements of the Programme with Anchorstone Consulting in order to protect the Programme's set objectives and anticipated benefits. Consultancy services from Anchorstone Consulting have previously been procured to support the Business Change and readiness deliverables, Anchorstone resource have also been involved in the recent technical design review and validation of the solution to ensure the Programme requirements have been met. Anchorstone Consulting also have a clear understanding of the detailed activities required to fully implement the Programme. CUG is now at a critical stage of delivery with the target date of delivering Employee Central, Payroll, ASK HR and SAP JAM for April/May 2022 followed quickly by Phase 2 deliverables (Learning, Succession, Talent, Performance and Compensation.) The Programme is in the middle of User Acceptance Testing and about to embark on Parallel Payroll running. From an efficiency and effectiveness perspective it would be beneficial for CUG to seek to extend the resource profile from Anchorstone Consulting to deliver the remaining elements of the Programme, this is due to their in-depth knowledge already gained. Any delay in pausing this Programme in order to go through a full procurement process would be detrimental to CUG, as this would result in further delay in the delivery of the Programme, resulting in additional costs being incurred, there is also a significant risk of losing internal staff and knowledge gained already on the Programme. SuccessFactors Modules to be fully designed, built, tested and Implemented in two phases: Phase 1: Employee Central, Payroll, Recruitment, Onboarding ASK HR, SAP JAM, Reporting. Target date is April/May 2022. Phase 2: Performance and Goal Management, Succession & Development, Learning, Compensation. Target date is July/August 2022. Note: Workforce Analytics is expected to be designed, built and tested by our current software Partner NTT. The Qualtrics costs for design and implementation has yet to be confirmed and may be delivered by Anchorstone Consulting."
},
"where": {
"section": "IV.1.2"
}
},
{
"newValue": {
"text": "Following the previous procurement of HR consultancy services on or around 2019, there is now an immediate need to progress at pace the remaining elements of the Programme with Anchorstone Consulting in order to protect the Programme's set objectives and anticipated benefits. Consultancy services from Anchorstone Consulting have previously been procured to support the Business Change and readiness deliverables, Anchorstone resource have also been involved in the recent technical design review and validation of the solution to ensure the Programme requirements have been met. Anchorstone Consulting also have a clear understanding of the detailed activities required to fully implement the Programme. CUG is now at a critical stage of delivery with the target date of delivering Employee Central, Payroll, ASK HR and SAP JAM for April/May 2022 followed quickly by Phase 2 deliverables (Learning, Succession, Talent, Performance and Compensation.) The Programme is in the middle of User Acceptance Testing and about to embark on Parallel Payroll running. From an efficiency and effectiveness perspective it would be beneficial for CUG to seek to extend the resource profile from Anchorstone Consulting to deliver the remaining elements of the Programme, this is due to their in-depth knowledge already gained. Any delay in pausing this Programme in order to go through a full procurement process would be detrimental to CUG, as this would result in further delay in the delivery of the Programme, resulting in additional costs being incurred, there is also a significant risk of losing internal staff and knowledge gained already on the Programme. SuccessFactors Modules to be fully designed, built, tested and Implemented in two phases: Phase 1: Employee Central, Payroll, Recruitment, Onboarding ASK HR, SAP JAM, Reporting. Target date is April/May 2022. Phase 2: Performance and Goal Management, Succession & Development, Learning, Compensation. Target date is July/August 2022. Note: Workforce Analytics is expected to be designed, built and tested by our current software Partner NTT. The Qualtrics costs for design and implementation has yet to be confirmed and may be delivered by Anchorstone Consulting."
},
"where": {
"section": "II.2.4"
}
}
]
}
]
},
"awards": [
{
"id": "002728-2022-1",
"relatedLots": [
"1"
],
"status": "active",
"suppliers": [
{
"id": "GB-FTS-42648",
"name": "Anchorstone Consulting"
}
]
}
],
"parties": [
{
"id": "GB-FTS-32803",
"name": "Coventry University",
"identifier": {
"legalName": "Coventry University"
},
"address": {
"streetAddress": "PRIORY STREET",
"locality": "COVENTRY",
"region": "UKG33",
"postalCode": "CV15FB",
"countryName": "United Kingdom"
},
"contactPoint": {
"email": "ad7164@coventry.ac.uk"
},
"roles": [
"buyer"
],
"details": {
"url": "http://www.coventry.ac.uk",
"classifications": [
{
"scheme": "TED_CA_TYPE",
"id": "BODY_PUBLIC",
"description": "Body governed by public law"
},
{
"scheme": "COFOG",
"id": "09",
"description": "Education"
}
]
}
},
{
"id": "GB-FTS-42648",
"name": "Anchorstone Consulting",
"identifier": {
"legalName": "Anchorstone Consulting"
},
"address": {
"locality": "Richmond",
"region": "UKI",
"countryName": "United Kingdom"
},
"roles": [
"supplier"
],
"details": {
"scale": "large"
}
},
{
"id": "GB-FTS-9377",
"name": "Coventry University",
"identifier": {
"legalName": "Coventry University"
},
"address": {
"locality": "Coventry",
"countryName": "United Kingdom"
},
"roles": [
"reviewBody"
]
}
],
"buyer": {
"id": "GB-FTS-32803",
"name": "Coventry University"
},
"contracts": [
{
"id": "002728-2022-1",
"awardID": "002728-2022-1",
"status": "active",
"value": {
"amount": 1307280,
"currency": "GBP"
},
"dateSigned": "2022-01-31T00:00:00Z"
}
],
"language": "en"
}