Notice Information
Notice Title
TfGM Ducting and Minor Highway Improvement Works Framework
Notice Description
(SCOOT/ MOVA) at various locations throughout the Greater Manchester conurbation. SCOOT is Split Cycle Offset Optimisation Technique. MOVA is Microprocessor Optimised Vehicle Actuation. To ensure implementation of adaptive traffic signal control (SCOOT/ MOVA) - To support this TfGM required two suitably experienced contractors to undertake associated civils enabling works on a call-off basis, in terms of ducting and other associated minor highways works. - The SCOOT/MOVA technology itself will then be installed via a separate Traffic Signal Maintenance contract already in place. - Following the award of Growth Deal 3 funding it is estimated that this level of funding will enable approximately 60nr junctions to be improved with site works to commence at the start of 2018 and last until the start of 2020. - Other additional funding may also be obtained during the term of the Framework that results in a requirement to undertake further works associated with traffic signal junction improvements, these may also be delivered via the framework. - The contractual arrangement is also intended to be made available for use by other authorities who may require works to be delivered via the framework subject to availability of funding. These include the ten members of the Association of Greater Manchester Authorities. -There is no guarantee given relating to the value of works to be instructed via this framework agreement.
Lot Information
Lot 1
(SCOOT/ MOVA) at various locations throughout the Greater Manchester conurbation. SCOOT is Split Cycle Offset Optimisation Technique. MOVA is Microprocessor Optimised Vehicle Actuation. To ensure implementation of adaptive traffic signal control (SCOOT/ MOVA) - To support this TfGM required two suitably experienced contractors to undertake associated civils enabling works on a call-off basis, in terms of ducting and other associated minor highways works. - The SCOOT/MOVA technology itself will then be installed via a separate Traffic Signal Maintenance contract already in place. - Following the award of Growth Deal 3 funding it is estimated that this level of funding will enable approximately 60nr junctions to be improved with site works to commence at the start of 2018 and last until the start of 2020. - Other additional funding may also be obtained during the term of the Framework that results in a requirement to undertake further works associated with traffic signal junction improvements, these may also be delivered via the framework. - The contractual arrangement is also intended to be made available for use by other authorities who may require works to be delivered via the framework subject to availability of funding. These include the ten members of the Association of Greater Manchester Authorities. -There is no guarantee given relating to the value of works to be instructed via this framework agreement.
Notice Details
Publication & Lifecycle
- Open Contracting ID
- ocds-h6vhtk-03335e
- Publication Source
- Find A Tender Service
- Latest Notice
- https://www.find-tender.service.gov.uk/Notice/011546-2023
- Current Stage
- Award
- All Stages
- Tender, Award
Procurement Classification
- Notice Type
- Tender Notice
- Procurement Type
- Framework
- Procurement Category
- Works
- Procurement Method
- Selective
- Procurement Method Details
- Restricted procedure
- Tender Suitability
- Not specified
- Awardee Scale
- SME
Common Procurement Vocabulary (CPV)
- CPV Divisions
45 - Construction work
-
- CPV Codes
45000000 - Construction work
Notice Value(s)
- Tender Value
- £200,000,000 £100M-£1B
- Lots Value
- £20,000,000 £10M-£100M
- Awards Value
- Not specified
- Contracts Value
- £20,000,000 £10M-£100M
Notice Dates
- Publication Date
- 21 Apr 20232 years ago
- Submission Deadline
- 2 Jun 2022Expired
- Future Notice Date
- Not specified
- Award Date
- 30 Mar 20232 years ago
- Contract Period
- Not specified - Not specified
- Recurrence
- Not specified
Notice Status
- Tender Status
- Complete
- Lots Status
- Cancelled
- Awards Status
- Active
- Contracts Status
- Active
Buyer & Supplier
Contracting Authority (Buyer)
- Main Buyer
- TRANSPORT FOR GREATER MANCHESTER
- Contact Name
- Ms Francesca Hibbert
- Contact Email
- francesca.hibbert@tfgm.com
- Contact Phone
- +44 1612441599
Buyer Location
- Locality
- MANCHESTER
- Postcode
- M1 3BG
- Post Town
- Manchester
- Country
- England
-
- Major Region (ITL 1)
- TLD North West (England)
- Basic Region (ITL 2)
- TLD3 Greater Manchester
- Small Region (ITL 3)
- TLD33 Manchester
- Delivery Location
- TLD North West (England)
-
- Local Authority
- Manchester
- Electoral Ward
- Piccadilly
- Westminster Constituency
- Manchester Central
Further Information
Open Contracting Data Standard (OCDS)
View full OCDS Record for this contracting process
The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.
{
"tag": [
"compiled"
],
"id": "ocds-h6vhtk-03335e-2023-04-21T15:31:30+01:00",
"date": "2023-04-21T15:31:30+01:00",
"ocid": "ocds-h6vhtk-03335e",
"initiationType": "tender",
"tender": {
"id": "DN604867",
"legalBasis": {
"id": "32014L0024",
"scheme": "CELEX"
},
"title": "TfGM Ducting and Minor Highway Improvement Works Framework",
"status": "complete",
"classification": {
"scheme": "CPV",
"id": "45000000",
"description": "Construction work"
},
"mainProcurementCategory": "works",
"description": "(SCOOT/ MOVA) at various locations throughout the Greater Manchester conurbation. SCOOT is Split Cycle Offset Optimisation Technique. MOVA is Microprocessor Optimised Vehicle Actuation. To ensure implementation of adaptive traffic signal control (SCOOT/ MOVA) - To support this TfGM required two suitably experienced contractors to undertake associated civils enabling works on a call-off basis, in terms of ducting and other associated minor highways works. - The SCOOT/MOVA technology itself will then be installed via a separate Traffic Signal Maintenance contract already in place. - Following the award of Growth Deal 3 funding it is estimated that this level of funding will enable approximately 60nr junctions to be improved with site works to commence at the start of 2018 and last until the start of 2020. - Other additional funding may also be obtained during the term of the Framework that results in a requirement to undertake further works associated with traffic signal junction improvements, these may also be delivered via the framework. - The contractual arrangement is also intended to be made available for use by other authorities who may require works to be delivered via the framework subject to availability of funding. These include the ten members of the Association of Greater Manchester Authorities. -There is no guarantee given relating to the value of works to be instructed via this framework agreement.",
"value": {
"amount": 200000000,
"currency": "GBP"
},
"lots": [
{
"id": "1",
"description": "(SCOOT/ MOVA) at various locations throughout the Greater Manchester conurbation. SCOOT is Split Cycle Offset Optimisation Technique. MOVA is Microprocessor Optimised Vehicle Actuation. To ensure implementation of adaptive traffic signal control (SCOOT/ MOVA) - To support this TfGM required two suitably experienced contractors to undertake associated civils enabling works on a call-off basis, in terms of ducting and other associated minor highways works. - The SCOOT/MOVA technology itself will then be installed via a separate Traffic Signal Maintenance contract already in place. - Following the award of Growth Deal 3 funding it is estimated that this level of funding will enable approximately 60nr junctions to be improved with site works to commence at the start of 2018 and last until the start of 2020. - Other additional funding may also be obtained during the term of the Framework that results in a requirement to undertake further works associated with traffic signal junction improvements, these may also be delivered via the framework. - The contractual arrangement is also intended to be made available for use by other authorities who may require works to be delivered via the framework subject to availability of funding. These include the ten members of the Association of Greater Manchester Authorities. -There is no guarantee given relating to the value of works to be instructed via this framework agreement.",
"awardCriteria": {
"criteria": [
{
"name": "Quality",
"type": "quality",
"description": "40"
},
{
"type": "price",
"description": "60"
}
]
},
"value": {
"amount": 20000000,
"currency": "GBP"
},
"contractPeriod": {
"durationInDays": 1440
},
"hasRenewal": false,
"submissionTerms": {
"variantPolicy": "notAllowed"
},
"hasOptions": false,
"status": "cancelled"
}
],
"items": [
{
"id": "1",
"deliveryAddresses": [
{
"region": "UKD"
},
{
"region": "UKD"
}
],
"relatedLot": "1"
}
],
"submissionMethod": [
"electronicSubmission"
],
"submissionMethodDetails": "http://procontract.due-north.com/register",
"procurementMethod": "selective",
"procurementMethodDetails": "Restricted procedure",
"techniques": {
"hasFrameworkAgreement": true,
"frameworkAgreement": {
"maximumParticipants": 1
}
},
"coveredBy": [
"GPA"
],
"tenderPeriod": {
"endDate": "2022-06-02T12:00:00+01:00"
},
"submissionTerms": {
"languages": [
"en"
]
},
"hasRecurrence": false,
"amendments": [
{
"id": "1",
"unstructuredChanges": [
{
"oldValue": {
"text": "Amendment - PS20,000,000"
},
"newValue": {
"text": "PS20,000,000"
},
"where": {
"section": "II.1.5",
"label": "Estimated Total Value"
}
}
]
},
{
"id": "2",
"unstructuredChanges": [
{
"newValue": {
"text": "To add following Participating Authorities: Official name Bolton Council _____ Postal address: Howell Croft North Town Bolton Postal code BL1 1QY Country United Kingdom (UK) -- ------------------- Official name Bury Council _____ Postal address: Town Hall, Knowsley Street Town Bury Postal code BL9 0SW Country United Kingdom (UK) -- -------------------"
},
"where": {
"section": "II.2.14"
}
}
]
}
]
},
"parties": [
{
"id": "GB-FTS-5677",
"name": "Transport for Greater Manchester",
"identifier": {
"legalName": "Transport for Greater Manchester"
},
"address": {
"streetAddress": "2 Piccadilly Place",
"locality": "Manchester",
"region": "UKD",
"postalCode": "M1 3BG",
"countryName": "United Kingdom"
},
"contactPoint": {
"name": "Ms Francesca Hibbert",
"telephone": "+44 1612441599",
"email": "francesca.hibbert@tfgm.com",
"url": "http://procontract.due-north.com/register"
},
"roles": [
"buyer"
],
"details": {
"url": "http://www.tfgm.com",
"buyerProfile": "http://www.tfgm.com",
"classifications": [
{
"scheme": "TED_CA_TYPE",
"id": "BODY_PUBLIC",
"description": "Body governed by public law"
},
{
"scheme": "COFOG",
"id": "01",
"description": "General public services"
}
]
}
},
{
"id": "GB-FTS-2508",
"name": "Transport for Greater Manchester",
"identifier": {
"legalName": "Transport for Greater Manchester"
},
"address": {
"locality": "Manchester",
"countryName": "United Kingdom"
},
"roles": [
"reviewBody"
]
},
{
"id": "GB-FTS-80877",
"name": "Rosgal Limited",
"identifier": {
"legalName": "Rosgal Limited"
},
"address": {
"streetAddress": "Progress House",
"locality": "Manchester",
"region": "UKD",
"postalCode": "M20 3BN",
"countryName": "United Kingdom"
},
"roles": [
"supplier"
],
"details": {
"scale": "sme"
}
},
{
"id": "GB-FTS-80878",
"name": "George Cox & Sons Ltd",
"identifier": {
"legalName": "George Cox & Sons Ltd"
},
"address": {
"streetAddress": "Hall Lane",
"locality": "Bolton",
"region": "UKD",
"postalCode": "BL4 7QF",
"countryName": "United Kingdom"
},
"roles": [
"supplier"
],
"details": {
"scale": "sme"
}
},
{
"id": "GB-FTS-80879",
"name": "Prescott Special Projects Ltd",
"identifier": {
"legalName": "Prescott Special Projects Ltd"
},
"address": {
"streetAddress": "50 Crabtree Lane",
"locality": "Lancashire",
"region": "UKD",
"postalCode": "L40 0RN",
"countryName": "United Kingdom"
},
"roles": [
"supplier"
],
"details": {
"scale": "sme"
}
}
],
"buyer": {
"id": "GB-FTS-5677",
"name": "Transport for Greater Manchester"
},
"language": "en",
"awards": [
{
"id": "011546-2023-1",
"relatedLots": [
"1"
],
"title": "TfGM Ducting and Minor Highway Improvement Works Framework",
"status": "active",
"suppliers": [
{
"id": "GB-FTS-80877",
"name": "Rosgal Limited"
}
]
},
{
"id": "011546-2023-2",
"relatedLots": [
"1"
],
"status": "active",
"suppliers": [
{
"id": "GB-FTS-80878",
"name": "George Cox & Sons Ltd"
}
]
},
{
"id": "011546-2023-3",
"relatedLots": [
"1"
],
"title": "TfGM Ducting and Minor Highway Improvement Works Framework",
"status": "active",
"suppliers": [
{
"id": "GB-FTS-80879",
"name": "Prescott Special Projects Ltd"
}
]
}
],
"contracts": [
{
"id": "011546-2023-1",
"awardID": "011546-2023-1",
"title": "TfGM Ducting and Minor Highway Improvement Works Framework",
"status": "active",
"value": {
"amount": 20000000,
"currency": "GBP"
},
"dateSigned": "2023-03-31T00:00:00+01:00"
},
{
"id": "011546-2023-2",
"awardID": "011546-2023-2",
"status": "active",
"value": {
"amount": 20000000,
"currency": "GBP"
},
"dateSigned": "2023-03-31T00:00:00+01:00"
},
{
"id": "011546-2023-3",
"awardID": "011546-2023-3",
"title": "TfGM Ducting and Minor Highway Improvement Works Framework",
"status": "active",
"value": {
"amount": 20000000,
"currency": "GBP"
},
"dateSigned": "2023-03-31T00:00:00+01:00"
}
],
"bids": {
"statistics": [
{
"id": "1",
"measure": "bids",
"relatedLot": "1",
"value": 10
},
{
"id": "2",
"measure": "bids",
"relatedLot": "1",
"value": 10
},
{
"id": "3",
"measure": "bids",
"relatedLot": "1",
"value": 10
}
]
}
}