Notice Information
Notice Title
Campus Development Programme Phase 1
Notice Description
The University of East Anglia was created during the 1960s. Its original campus buildings were designed by the acclaimed architect Sir Denys Lasdun and several of the original buildings are now Grade II Listed, including the original teaching and science building the 'Lasdun Wall'. The Grade II listed Lasdun Wall is an iconic and important part of University of East Anglia's (UEA) history situated in the centre of the UEA's vibrant and busy 24/7 campus. However, the building needs repair and refurbishment to address condition issues and to deliver essential sustainability improvements to enable the University to meet their target to be a net zero campus by 2045. The Lasdun Wall comprises four buildings constructed to appear as one (Building 3, Building 4, Building 5 and Building 6). The University plans to carry out a four-phase strip-back-to frame refurbishment of the Lasdun Wall. This project - Lasdun Wall Refurbishment Phase 1 - will deliver new modern science facilities and teaching space in an extended Building 3, whilst existing science research facilities continue to operate within Buildings 4, 5 and 6. The existing science facilities are currently at risk due to potential condition failures of the buildings, therefore the success of Phase 1 to 'de-risk' highly specialised facilities within the Lasdun wall, is of extreme importance to the University. The University's "Phase 1" project consists of three elements: * Preliminary enabling works (by others) * The Main Works (the subject of this contract) * A package of interphase enabling works which will complete Phase 1 and prepare for the future decommissioning of Buildings The appointed Main Contractor will be required to undertake the following: Initial phase of strip out and asbestos removal will have been undertaken to provide an empty shell, however asbestos removal will be required by the main contractor as follows: * Facades - Around existing windows which will be replaced, and concrete facade panels removed to accommodate the new extension. * Existing floor screed abutting the perimeter which includes asbestos contamination around existing fixings to the retained listed concrete facade panels - fixings and all remaining screeds will need to be removed. * Asbestos removal Extension - An extension of approx. 2,966m2 is planned to one elevation. Window Replacement and Facade Treatment Fitting Out of existing building - The re-fit comprises circa 11,287m2 of space split to include science research facilities and teaching and social learning space. External Works
Lot Information
Lot 1
The University of East Anglia was created during the 1960s. Its original campus buildings were designed by the acclaimed architect Sir Denys Lasdun and several of the original buildings are now Grade II Listed, including the original teaching and science building the 'Lasdun Wall'. The Grade II listed Lasdun Wall is an iconic and important part of University of East Anglia's (UEA) history situated in the centre of the UEA's vibrant and busy 24/7 campus. However, the building needs repair and refurbishment to address condition issues and to deliver essential sustainability improvements to enable the University to meet their target to be a net zero campus by 2045. The Lasdun Wall comprises four buildings constructed to appear as one (Building 3, Building 4, Building 5 and Building 6). The University plans to carry out a four-phase strip-back-to frame refurbishment of the Lasdun Wall. This project - Lasdun Wall Refurbishment Phase 1 - will deliver new modern science facilities and teaching space in an extended Building 3, whilst existing science research facilities continue to operate within Buildings 4, 5 and 6. The existing science facilities are currently at risk due to potential condition failures of the buildings, therefore the success of Phase 1 to 'de-risk' highly specialised facilities within the Lasdun wall, is of extreme importance to the University. The University's "Phase 1" project consists of three elements: * Preliminary enabling works (by others) * The Main Works (the subject of this contract) * A package of interphase enabling works which will complete Phase 1 and prepare for the future decommissioning of Buildings The appointed Main Contractor will be required to undertake the following: Initial phase of strip out and asbestos removal will have been undertaken to provide an empty shell, however asbestos removal will be required by the main contractor as follows: * Facades - Around existing windows which will be replaced, and concrete facade panels removed to accommodate the new extension. * Existing floor screed abutting the perimeter which includes asbestos contamination around existing fixings to the retained listed concrete facade panels - fixings and all remaining screeds will need to be removed. * Asbestos removal Extension - An extension of approx. 2,966m2 is planned to one elevation. Window Replacement and Facade Treatment Fitting Out of existing building - The re-fit comprises circa 11,287m2 of space split to include science research facilities and teaching and social learning space. External Works
Notice Details
Publication & Lifecycle
- Open Contracting ID
- ocds-h6vhtk-04161e
- Publication Source
- Find A Tender Service
- Latest Notice
- https://www.find-tender.service.gov.uk/Notice/024238-2024
- Current Stage
- Award
- All Stages
- Tender, Award
Procurement Classification
- Notice Type
- Tender Notice
- Procurement Type
- Standard
- Procurement Category
- Works
- Procurement Method
- Selective
- Procurement Method Details
- Competitive procedure with negotiation
- Tender Suitability
- Not specified
- Awardee Scale
- Large
Common Procurement Vocabulary (CPV)
- CPV Divisions
45 - Construction work
-
- CPV Codes
45000000 - Construction work
Notice Value(s)
- Tender Value
- Not specified
- Lots Value
- Not specified
- Awards Value
- Not specified
- Contracts Value
- £87,983,160 £10M-£100M
Notice Dates
- Publication Date
- 2 Aug 20241 years ago
- Submission Deadline
- 6 Dec 2023Expired
- Future Notice Date
- Not specified
- Award Date
- 23 Jul 20241 years ago
- Contract Period
- Not specified - Not specified
- Recurrence
- Not specified
Notice Status
- Tender Status
- Complete
- Lots Status
- Cancelled
- Awards Status
- Active
- Contracts Status
- Active
Buyer & Supplier
Contracting Authority (Buyer)
- Main Buyer
- UNIVERSITY OF EAST ANGLIA
- Contact Name
- Claire Woodcroft
- Contact Email
- c.woodcroft@uea.ac.uk
- Contact Phone
- +44 1603592728
Buyer Location
- Locality
- NORWICH
- Postcode
- NR4 7TJ
- Post Town
- Norwich
- Country
- England
-
- Major Region (ITL 1)
- TLH East (England)
- Basic Region (ITL 2)
- TLH5 Norfolk
- Small Region (ITL 3)
- TLH51 Norwich and East Norfolk
- Delivery Location
- TLH15 Norwich and East Norfolk
-
- Local Authority
- Norwich
- Electoral Ward
- University
- Westminster Constituency
- Norwich South
Further Information
Open Contracting Data Standard (OCDS)
View full OCDS Record for this contracting process
The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.
{
"tag": [
"compiled"
],
"id": "ocds-h6vhtk-04161e-2024-08-02T09:43:41+01:00",
"date": "2024-08-02T09:43:41+01:00",
"ocid": "ocds-h6vhtk-04161e",
"description": "The anticipated programme is as follows: PCSA Start: 24th July 2024 PCSA End: 01st October 2024 Construction Start: 30th October 2024 Construction End: 14th January 2027",
"initiationType": "tender",
"tender": {
"id": "PURCON2023",
"legalBasis": {
"id": "32014L0024",
"scheme": "CELEX"
},
"title": "Campus Development Programme Phase 1",
"status": "complete",
"classification": {
"scheme": "CPV",
"id": "45000000",
"description": "Construction work"
},
"mainProcurementCategory": "works",
"description": "The University of East Anglia was created during the 1960s. Its original campus buildings were designed by the acclaimed architect Sir Denys Lasdun and several of the original buildings are now Grade II Listed, including the original teaching and science building the 'Lasdun Wall'. The Grade II listed Lasdun Wall is an iconic and important part of University of East Anglia's (UEA) history situated in the centre of the UEA's vibrant and busy 24/7 campus. However, the building needs repair and refurbishment to address condition issues and to deliver essential sustainability improvements to enable the University to meet their target to be a net zero campus by 2045. The Lasdun Wall comprises four buildings constructed to appear as one (Building 3, Building 4, Building 5 and Building 6). The University plans to carry out a four-phase strip-back-to frame refurbishment of the Lasdun Wall. This project - Lasdun Wall Refurbishment Phase 1 - will deliver new modern science facilities and teaching space in an extended Building 3, whilst existing science research facilities continue to operate within Buildings 4, 5 and 6. The existing science facilities are currently at risk due to potential condition failures of the buildings, therefore the success of Phase 1 to 'de-risk' highly specialised facilities within the Lasdun wall, is of extreme importance to the University. The University's \"Phase 1\" project consists of three elements: * Preliminary enabling works (by others) * The Main Works (the subject of this contract) * A package of interphase enabling works which will complete Phase 1 and prepare for the future decommissioning of Buildings The appointed Main Contractor will be required to undertake the following: Initial phase of strip out and asbestos removal will have been undertaken to provide an empty shell, however asbestos removal will be required by the main contractor as follows: * Facades - Around existing windows which will be replaced, and concrete facade panels removed to accommodate the new extension. * Existing floor screed abutting the perimeter which includes asbestos contamination around existing fixings to the retained listed concrete facade panels - fixings and all remaining screeds will need to be removed. * Asbestos removal Extension - An extension of approx. 2,966m2 is planned to one elevation. Window Replacement and Facade Treatment Fitting Out of existing building - The re-fit comprises circa 11,287m2 of space split to include science research facilities and teaching and social learning space. External Works",
"lots": [
{
"id": "1",
"description": "The University of East Anglia was created during the 1960s. Its original campus buildings were designed by the acclaimed architect Sir Denys Lasdun and several of the original buildings are now Grade II Listed, including the original teaching and science building the 'Lasdun Wall'. The Grade II listed Lasdun Wall is an iconic and important part of University of East Anglia's (UEA) history situated in the centre of the UEA's vibrant and busy 24/7 campus. However, the building needs repair and refurbishment to address condition issues and to deliver essential sustainability improvements to enable the University to meet their target to be a net zero campus by 2045. The Lasdun Wall comprises four buildings constructed to appear as one (Building 3, Building 4, Building 5 and Building 6). The University plans to carry out a four-phase strip-back-to frame refurbishment of the Lasdun Wall. This project - Lasdun Wall Refurbishment Phase 1 - will deliver new modern science facilities and teaching space in an extended Building 3, whilst existing science research facilities continue to operate within Buildings 4, 5 and 6. The existing science facilities are currently at risk due to potential condition failures of the buildings, therefore the success of Phase 1 to 'de-risk' highly specialised facilities within the Lasdun wall, is of extreme importance to the University. The University's \"Phase 1\" project consists of three elements: * Preliminary enabling works (by others) * The Main Works (the subject of this contract) * A package of interphase enabling works which will complete Phase 1 and prepare for the future decommissioning of Buildings The appointed Main Contractor will be required to undertake the following: Initial phase of strip out and asbestos removal will have been undertaken to provide an empty shell, however asbestos removal will be required by the main contractor as follows: * Facades - Around existing windows which will be replaced, and concrete facade panels removed to accommodate the new extension. * Existing floor screed abutting the perimeter which includes asbestos contamination around existing fixings to the retained listed concrete facade panels - fixings and all remaining screeds will need to be removed. * Asbestos removal Extension - An extension of approx. 2,966m2 is planned to one elevation. Window Replacement and Facade Treatment Fitting Out of existing building - The re-fit comprises circa 11,287m2 of space split to include science research facilities and teaching and social learning space. External Works",
"contractPeriod": {
"startDate": "2024-07-22T00:00:00+01:00"
},
"hasRenewal": false,
"secondStage": {
"minimumCandidates": 3,
"maximumCandidates": 3
},
"submissionTerms": {
"variantPolicy": "notAllowed"
},
"hasOptions": false,
"status": "cancelled",
"awardCriteria": {
"criteria": [
{
"name": "Quality",
"type": "quality",
"description": "30"
},
{
"type": "price",
"description": "70"
}
]
}
}
],
"items": [
{
"id": "1",
"additionalClassifications": [
{
"scheme": "CPV",
"id": "45000000",
"description": "Construction work"
}
],
"deliveryAddresses": [
{
"region": "UKH15"
},
{
"region": "UKH15"
}
],
"deliveryLocation": {
"description": "University of East Anglia campus, Norwich Research Park, Norwich. NR4 7TJ"
},
"relatedLot": "1"
}
],
"submissionMethod": [
"electronicSubmission"
],
"submissionMethodDetails": "https://in-tendhost.co.uk/universityofeastanglia/aspx/Home",
"documents": [
{
"id": "economic",
"documentType": "economicSelectionCriteria"
},
{
"id": "technical",
"documentType": "technicalSelectionCriteria"
}
],
"otherRequirements": {
"requiresStaffNamesAndQualifications": true
},
"procurementMethod": "selective",
"procurementMethodDetails": "Competitive procedure with negotiation",
"secondStage": {
"noNegotiationNecessary": true,
"invitationDate": "2024-01-15T00:00:00Z"
},
"tenderPeriod": {
"endDate": "2023-12-06T12:00:00Z"
},
"submissionTerms": {
"languages": [
"en"
],
"bidValidityPeriod": {
"durationInDays": 90
}
},
"hasRecurrence": false,
"contractTerms": {
"electronicInvoicingPolicy": "allowed"
},
"coveredBy": [
"GPA"
]
},
"parties": [
{
"id": "GB-COH-RC000651",
"name": "UNIVERSITY OF EAST ANGLIA",
"identifier": {
"legalName": "UNIVERSITY OF EAST ANGLIA",
"id": "RC000651",
"scheme": "GB-COH"
},
"address": {
"streetAddress": "Norwich Research Park,Earlham Road",
"locality": "NORWICH",
"region": "UKH15",
"postalCode": "NR47TJ",
"countryName": "United Kingdom"
},
"contactPoint": {
"name": "Claire Woodcroft",
"telephone": "+44 1603592728",
"email": "c.woodcroft@uea.ac.uk",
"url": "https://in-tendhost.co.uk/universityofeastanglia/aspx/Home"
},
"roles": [
"buyer"
],
"details": {
"url": "https://www.uea.ac.uk",
"classifications": [
{
"scheme": "TED_CA_TYPE",
"id": "BODY_PUBLIC",
"description": "Body governed by public law"
},
{
"scheme": "COFOG",
"id": "09",
"description": "Education"
}
]
}
},
{
"id": "GB-FTS-1404",
"name": "University of East Anglia",
"identifier": {
"legalName": "University of East Anglia"
},
"address": {
"locality": "Norwich",
"postalCode": "NR4 7TJ",
"countryName": "United Kingdom"
},
"roles": [
"reviewBody"
]
},
{
"id": "GB-COH-9887082",
"name": "Mace Construction Ltd",
"identifier": {
"legalName": "Mace Construction Ltd",
"id": "9887082",
"scheme": "GB-COH"
},
"address": {
"streetAddress": "155 Moorgate",
"locality": "London",
"region": "UKI",
"postalCode": "EC2M 6XB",
"countryName": "United Kingdom"
},
"roles": [
"supplier"
],
"details": {
"scale": "large"
}
},
{
"id": "GB-FTS-14520",
"name": "University of East Anglia",
"identifier": {
"legalName": "University of East Anglia"
},
"address": {
"streetAddress": "Norwich Research Park",
"locality": "Norwich",
"postalCode": "NR4 7TJ",
"countryName": "United Kingdom"
},
"roles": [
"reviewBody"
]
}
],
"buyer": {
"id": "GB-COH-RC000651",
"name": "UNIVERSITY OF EAST ANGLIA"
},
"language": "en",
"awards": [
{
"id": "024238-2024-1",
"relatedLots": [
"1"
],
"status": "active",
"suppliers": [
{
"id": "GB-COH-9887082",
"name": "Mace Construction Ltd"
}
]
}
],
"contracts": [
{
"id": "024238-2024-1",
"awardID": "024238-2024-1",
"status": "active",
"value": {
"amount": 87983160.82,
"currency": "GBP"
},
"dateSigned": "2024-07-24T00:00:00+01:00"
}
],
"bids": {
"statistics": [
{
"id": "1",
"measure": "bids",
"relatedLot": "1",
"value": 2
}
]
}
}