Summary of the contracting process

East West Rail Company Limited is procuring client support services for developing and delivering the East West Rail programme, which will create and upgrade rail links between Oxford, Milton Keynes, Bedford and Cambridge. The work is divided into three lots: programme reporting, planning, cost and risk controls, and project management office support; commercial management, procurement support and contract administration; and project and construction management, including site inspection, quality, health and safety, and CDM compliance. The services support a major rail infrastructure programme and its governance, assurance and delivery. The work is for East West Rail across the United Kingdom. The authority is also procuring a separate integration, technical, operations, assurance and environmental partner; client support suppliers must remain structurally separate from that partner during their contracts to protect independent advice and assurance.

The buyer invited offers through a selective competitive flexible procedure, with expressions of interest and conflict-of-interest checks followed by a procurement-specific questionnaire, tender stage for shortlisted suppliers and optional negotiation. Expressions of interest were due by 13 November 2026 at 12:00; enquiries by 6 November 2026 at 12:00. The completed questionnaire deadline is 24 February 2027, and the questionnaire was scheduled for issue on 30 November 2026. The estimated total value is £230 million to £350 million; stated lot values are £127 million for reporting and controls, £72 million for commercial management, and £151 million for project and construction management. Each lot is planned for 1 May 2028 to 30 April 2040. One supplier may be awarded at most one lot. Evaluation weights technical quality at 60%, price at 30% and social value at 10%.

The opportunity suits consultancies and delivery partners able to provide specialist support across a complex rail infrastructure programme, with capacity to meet the requirements of the lot or lots pursued. Lot 1 calls for strength in integrated cost, schedule, risk and change reporting; master scheduling, quantitative risk analysis, earned value and digital reporting, including Power BI and data governance. Lot 2 suits commercial and contract-management teams experienced in procurement, cost estimating, NEC or equivalent contract administration, payment assessment, change control, claims avoidance and audit support. Lot 3 requires project and package coordination, stakeholder and interface management, mobilisation, progress reporting and construction oversight, including site inspection, quality, health and safety and CDM compliance. Legal and financial capacity, technical ability and conflict-of-interest declarations are assessed; an Ethical Walls Agreement applies to relevant parties. SMEs and voluntary, community and social enterprises are identified as suitable. Suppliers must account for separation from the separately appointed assurance partner and award interaction constraints.

How relevant is this notice?

Notice Information

Notice Title

Client Support Framework (CSF)

Notice Description

The East West Railway Company (the Authority) is responsible for the delivery of East West Rail (EWR), a Nationally Significant Infrastructure Project providing new and upgraded rail links between Oxford, Milton Keynes, Bedford and Cambridge. EWR Co. is responsible for leading the development, procurement, and commissioning of the railway. The Authority is undertaking a procurement for Client Support Framework (CSF) Partners to support the development and delivery of the EWR programme. Overview of the Intended Contract The Authority is establishing a 3 lot / single appointed supplier per lot framework for the provision of Client Support Services (CSF) for a period of twelve (12) years. Relationship with the ITOAE Partner The Authority is separately procuring an Integration, Technical, Operations, Assurance and Environmental (ITOAE) Partner. The Authority's current position is that the CSF partners will be structurally separated from the ITOAE, such that the appointed CSF Partners will not be eligible to be appointed under the ITOAE for the duration of the CSF contracts. The purpose of this separation is to protect the independence of assurance and advice, to mitigate real or perceived conflicts of interest, and to align with independent review findings on major programme governance (including the Stewart Review, 2025). The Conditions of Participation are :- Stage 0 - Expression of Interest and Ethical Walls Agreement where relevant. Stage 1 - PSQ stage to include Legal and Financial Capacity , Conflict of Interest declarations and Technical ability. Stage 2 - ITT stage for shortlisted suppliers to include Quality and Commercial evaluation. Stage 3 - Optional negotiation. All be set in accordance with the Authority's obligations under the Procurement Act 2023 and the Procurement Regulations 2024. Scope of Services At this stage , the Authority has defined the high-level scope of services. Lot 1 - Reporting and Controls / PMO Support Programme, portfolio and package level reporting: * integrated cost, schedule, risk, opportunity and change performance reporting; * executive dashboards, KPI scorecards and delivery confidence assessments; * consolidated programme performance reporting aligned to EWR governance and reporting cycles. Planning and scheduling support: * development, maintenance and assurance of integrated master schedules and performance baselines; * critical path, float, milestone, recovery and scenario analysis; * schedule risk analysis and integrated planning standards support. Cost and performance controls: * delivery cost forecasting, ETC/EAC management and performance reporting; * reconciliation of cost, schedule, risk and change baselines; * trend analysis, earned value management and early warning indicators. Risk, issue and opportunity management support: * maintenance of programme risk, issue and opportunity registers within ARM; * quantitative schedule and cost risk analysis (QSRA/QCRA) support; * risk reporting, mitigation tracking, assurance coordination and escalation management. Governance, assurance and management information (MI): * Board, Executive, Sponsor and DfT reporting and governance support; * stage gate, assurance, change governance and gateway readiness activities; * standardised reporting products, evidence packs and audit-ready decision records. Controls systems, data governance and digital reporting: * administration and optimisation of planning, cost, risk and reporting toolsets; * Power BI reporting environments, automated reporting and data analytics; * data governance, quality assurance, configuration control and document management interfaces. Lot 2 - Commercial Management and Contract Administration support Procurement support: * pre tender estimation; * commercial evaluation; * commercial support during tender processes. Contract administration: * management of notices, instructions, early warnings and compensation events; * administration of NEC (or equivalent) processes; * maintenance of contractual registers and correspondence logs. Change control and forecasting support: * cost planning, estimating and cost engineering; * development and maintenance of cost estimates; * assessment and logging of change events; * affordability and cost assurance of options. Payment and cost management support: * valuation support; * payment application assessment; * reconciliation against cost records. Claims avoidance and dispute support: * contemporaneous record management; * support to dispute resolution processes; * preparation of evidence packs (without advocacy role unless instructed). Supplier performance and compliance monitoring: * performance data collation against contractual KPIs; * payment practice and supply chain compliance checks. Commercial data and audit support: * audit responses and evidence collation; * benchmarking and affordability analyses. Lot 3 - Project & Construction Management Support Project and package management support: * workstream coordination and day to day management support; * delivery plan development and tracking; * action management and follow up; * Interface and dependency management; * coordination across contractors, designers, third parties and stakeholders; * management of interface schedules and logs. Programme governance support: * preparation of governance boards and working groups; * action and decision tracking; * support to stage gate and readiness reviews. Stakeholder and third party coordination, including: * support to statutory undertaker, local authority and regulator engagement; * tracking of commitments and undertakings. Transition and mobilisation support: * support to phase transitions (e.g. design to construction); * readiness planning and handover coordination. Delivery performance support: * progress measurement and reporting; * recovery planning support (without authority to direct suppliers). Construction Management: * Clerk of works/Site Inspector * Construction Supervisor/Compliance Manager * Quality Assurance * Health & Safety * CDM compliance. This procurement will be run concurrently with others. Bidders may tender for any or all of the Lots/Contracts identified in the table shown in Package Bidding and Award Constraints letter. This approach is intended to support market participation and allow bidders to put forward appropriate delivery solutions. However, submitting tenders for multiple Lots/Contracts across the Procurements does not mean a bidder will be eligible to be awarded all Lots/Contracts. Award decisions will be subject to the Lot/Contract interaction rules set out in the letter, which are intended to: * Maintain independence between assurance, management and delivery functions. * Avoid conflicts of interest. * Prevent excessive concentration of specialist services within a single organisation. * Preserve effective commercial oversight. * Ensure suppliers have sufficient capacity and capability to successfully deliver awarded contracts. Please ensure you refer to Package Bidding and Award Constraints letter for further detail. * Contract Form - NEC4 Professional Service Contract * Estimated total value - PS230 million -PS350 million

Lot Information

Reporting and Controls / PMO Support

Programme, portfolio and package level reporting: * integrated cost, schedule, risk, opportunity and change performance reporting; * executive dashboards, KPI scorecards and delivery confidence assessments; * consolidated programme performance reporting aligned to EWR governance and reporting cycles. Planning and scheduling support: * development, maintenance and assurance of master and integrated schedules; * critical path, float and scenario analysis; * schedule change control support. Cost and performance controls: * cost forecasting and EAC support; * reconciliation of cost, schedule and scope baselines; * trend analysis and early warning indicators. Risk, issue and opportunity management support: * maintenance of programme and workstream risk registers; * quantitative risk analysis (QRA) support; * interface with assurance and gateway preparation. Management information (MI) production: * Board, Sponsor and DfT packs; * standardised reporting templates and data definitions; * audit ready evidence trails. Controls systems and data governance: * toolset configuration and administration (e.g. planning, cost, risk tools); * data quality checks and consistency rules; * document and records management interfaces.

Commercial Management and Contract Administration Support

Procurement support: * pre tender estimation; * commercial evaluation; * commercial support during tender processes. Contract administration: * management of notices, instructions, early warnings and compensation events; * administration of NEC (or equivalent) processes; * maintenance of contractual registers and correspondence logs. Change control and forecasting support: * cost planning, estimating and cost engineering; * development and maintenance of cost estimates; * assessment and logging of change events; * affordability and cost assurance of options. Payment and cost management support: * valuation support; * payment application assessment; * reconciliation against cost records. Claims avoidance and dispute support: * contemporaneous record management; * support to dispute resolution processes; * preparation of evidence packs (without advocacy role unless instructed). Supplier performance and compliance monitoring: * performance data collation against contractual KPIs; * payment practice and supply chain compliance checks. Commercial data and audit support: * audit responses and evidence collation; * benchmarking and affordability analyses.

Project & Construction Management Support

Project and package management support: * workstream coordination and day to day management support; * delivery plan development and tracking; * action management and follow up; * Interface and dependency management; * coordination across contractors, designers, third parties and stakeholders; * management of interface schedules and logs. Programme governance support: * preparation of governance boards and working groups; * action and decision tracking; * support to stage gate and readiness reviews. Stakeholder and third party coordination, including: * support to statutory undertaker, local authority and regulator engagement; * tracking of commitments and undertakings. Transition and mobilisation support: * support to phase transitions (e.g. design to construction); * readiness planning and handover coordination. Delivery performance support: * progress measurement and reporting; * recovery planning support (without authority to direct suppliers). Construction Management: * Clerk of works/Site Inspector * Construction Supervisor/Compliance Manager * Quality Assurance * Health & Safety * CDM compliance.

Planning Information

Objectives This preliminary market engagement under s16 PA23 is being undertaken to: • Inform the market by way of a market engagement presentation outlining the proposed procurement for a 12-year single supplier per lot / 3 Lot CSF Partner model, including breakpoints at Years 3, 6, and 9. • To invite interested parties to raise clarification questions by Wednesday 21st October 2026 which will be collated and responses made to all interested parties unless agreed as confidential. • Confirm if the approach is in line with the market offering and to inform East West Rail in finalising the proposed tender activity. Key Dates • Registration Deadline – Tuesday 20th October 2026, 17:00 • Market Clarification Deadline – Thursday 22nd October 2026, 17:00 • EWR Response to Clarification Deadline – Wednesday 28th October 2026, 17:00 To register interest, potential suppliers should: • Register on the Authority's Jaggaer e-procurement portal, if not already registered East West Rail https://eastwestrail.ukp.app.jaggaer.com/esop/ogc-host/public/eastwestrail/web/login.jst?_ncp=1791885132105.1056374-1 • Express interest in this preliminary market engagement via the Jaggaer portal by the registration deadline above, review presentation and forward clarifications via the Jaggaer portal. On confirmation of registration, participants will receive a briefing presentation, setting out the Authority's current programme context, indicative scope of services, and proposed commercial approach. The presentation will provide the information necessary to brief the interested parties about the proposed procurement. EWR is happy to seek clarifications about the proposed procurement which may include views from the market as to our proposed approach. Points to Note Please note the following important points before registering an interest: 1. This PME is not a call for competition and is not published with the intention of reducing any time limits for the receipt of tenders. 2. EWR Co. reserves the right not to commence any procurement process or award any contracts in respect of the EWR project and to amend the requirements stated in this PME (or as stated in any pre-procurement market engagement documents). 3. EWR Co. will provide information on its emerging thinking on scope, commercial structure, and contracting approach via the briefing presentation and within the pre-procurement market engagement documents made available to registered suppliers. EWR Co. reserves the right to further develop and change the procurement strategy and/or other aspects of the proposed procurement and delivery strategy as a result of pre-procurement market engagement or otherwise. 4. EWR Co. may undertake further pre-procurement market consultation exercises. 5. Publication of this PME is part of the Authority's due diligence process on its options, and the publication of this PME does not indicate that a decision has been made on a particular route for a procurement and/or subsequent contract award, if any. 6. Registration does not bind EWR Co. to include any party in the pre-procurement market engagement exercise. 7. EWR Co. is not obliged to communicate with any parties that register after the deadline for registration has passed. 8. EWR Co. is not obliged to respond to any correspondence on this notice or any matter related to this preliminary market engagement exercise. The decision to accept the registration of any interested party, and subsequent inclusion in any engagement process, shall remain with EWR Co. alone. 9. Non-participation in this process will not prevent any party from participating in any procurement process in due course. Participation will not confer any advantage or disadvantage in any future procurement process. 10. Given the early stage of the programme and the anticipated impact of the market engagement process and other internal processes, any information provided to the market shall be subject to change. EWR Co. (insofar as it is permitted by law) shall not be liable for any losses incurred by any party as a result of reliance on such information. 11. Any values set out in this PME are indicative and subject to revision and to confirmation in any future notices in relation to EWR procurement.

Notice Details

Publication & Lifecycle

Open Contracting ID
ocds-h6vhtk-06a433
Publication Source
Find A Tender Service
Latest Notice
https://www.find-tender.service.gov.uk/Notice/103450-2026
Current Stage
Tender
All Stages
Planning, Tender

Procurement Classification

Notice Type
UK4 - Tender Notice
Procurement Type
Framework
Procurement Category
Services
Procurement Method
Selective
Procurement Method Details
Competitive flexible procedure
Tender Suitability
SME, VCSE
Awardee Scale
Not specified

Common Procurement Vocabulary (CPV)

CPV Divisions

71 - Architectural, construction, engineering and inspection services

72 - IT services: consulting, software development, Internet and support

79 - Business services: law, marketing, consulting, recruitment, printing and security

98 - Other community, social and personal services


CPV Codes

71242000 - Project and design preparation, estimation of costs

71244000 - Calculation of costs, monitoring of costs

71248000 - Supervision of project and documentation

71300000 - Engineering services

71310000 - Consultative engineering and construction services

71311200 - Transport systems consultancy services

71311230 - Railway engineering services

71311300 - Infrastructure works consultancy services

71317210 - Health and safety consultancy services

71541000 - Construction project management services

72224000 - Project management consultancy services

79212000 - Auditing services

79212300 - Statutory audit services

79418000 - Procurement consultancy services

79994000 - Contract administration services

98511000 - Services of commercial workers

Notice Value(s)

Tender Value
£350,000,000 £100M-£1B
Lots Value
£350,000,000 £100M-£1B
Awards Value
Not specified
Contracts Value
Not specified

Notice Dates

Publication Date
30 Oct 20263 days ago
Submission Deadline
Not specified
Future Notice Date
30 Oct 2026Expired
Award Date
Not specified
Contract Period
1 May 2028 - 30 Apr 2040 Over 5 years
Recurrence
Not specified

Notice Status

Tender Status
Active
Lots Status
Active
Awards Status
Not Specified
Contracts Status
Not Specified

Buyer & Supplier

Contracting Authority (Buyer)

Main Buyer
East West Rail Company Limited
Contact Name
Available with D3 Tenders Premium →
Contact Email
Available with D3 Tenders Premium →
Contact Phone
Available with D3 Tenders Premium →

Buyer Location

Locality
MILTON KEYNES
Postcode
MK9 1EN
Postcode Area
Milton Keynes
Country
England

Major Region (ITL 1)
TLJ South East (England)
Basic Region (ITL 2)
TLJ1 Berkshire, Buckinghamshire and Oxfordshire
Small Region (ITL 3)
TLJ12 Milton Keynes
Delivery Location
Not specified

Local Authority
Milton Keynes
Electoral Ward
Central Milton Keynes
Westminster Constituency
Milton Keynes Central

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

JSON Markdown

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

Loading OCDS record...