This public procurement record has 2 releases in its history.

Award

05 Nov 2026 at 14:42

Award

05 Nov 2026 at 13:26

Summary of the contracting process

West Midlands Combined Authority is procuring the next engineering design stage and enabling works for upgrades to Witton and Aston railway stations in Birmingham. The work continues design development from Engineering Stages 3 and 4 into Stage 5 detailed design, alongside early works needed to prepare for the main construction phase. The scope includes railway surveys and technical assurance, overhead line equipment isolation planning and works, and preliminary, contingency, property and planning activities associated with the Waterworks site. The upgrades are intended to improve the stations ahead of major football matches at nearby Villa Park. This combines rail engineering consultancy and construction-related works, including site investigation, construction supervision and management, and infrastructure works. The delivery location is the West Midlands.

The procurement has been awarded to Network Rail Infrastructure, following a direct award by West Midlands Combined Authority. The authority selected Network Rail to continue work from the earlier design stages, citing continuity, avoidance of duplicated work, Network Rail’s ownership of the affected land and railway assets, and its role in technical assurance, safety, access and operational approvals. The award was made on 30 October 2026. Its value is £4,221,520 excluding VAT (£5,065,824 including VAT). The contract is scheduled to run from 17 November 2026 to 16 November 2027. The process was treated as a single lot. The stated purpose is to complete the interventions ahead of UEFA Euro 2028, with detailed design and enabling activities proceeding in parallel.

This award shows demand for integrated railway design development and enabling work on operational stations, where designs must fit existing assets and meet railway standards, safety controls and operational constraints. A credible competitor for similar work would need strong rail engineering capability across detailed design, surveys, technical assurance and construction planning, as well as the ability to coordinate overhead line equipment isolation and interfaces with live infrastructure. Experience securing railway access, permits and possessions, and managing asset-owner approvals, would be central to reducing programme and delivery risk. The buyer’s chosen route also shows the importance of continuity with earlier design work and established project knowledge. Suppliers without direct control of railway assets would need a clear approach to working within the asset owner’s assurance and approval processes.

How relevant is this notice?

Notice Information

Notice Title

Engineering Stage 5 (ES5) and Enabling Works for upgrade to Witton and Aston Rail Stations

Notice Description

The upgrade of Witton and Aston stations was identified as a Mayoral priority in April 2025, with delivery of the interventions to be completed ahead of the UEFA Euro 2028, which nearby Villa Park Stadium is set to host four international football matches. We are now proposing to continue the development phase into Engineering Stage 5 with Network Rail and in parallel commence advanced enabling works activities ahead of a targeted completion ahead of UEFA Euro 2028. Design Development The project has proceeded through design stages ES3 and ES4 and now needs to progress to detailed design. This is Engineering Stage 5 (ES5) in Network Rail's PACE framework. Additional elements for the next design phase include Overhead Line Equipment (OLE) isolation works to minimise disruption to the network in advance of the enabling works and core construction work phases, preliminary / personnel costs, contingency, and property and planning costs associated with the Waterworks site. Enabling Works Need To achieve programme and completion in advance of UEFA Euro 2028, enabling works are required in parallel to ES5 (detailed design) development.

Procurement Information

Additional or repeat goods, services or works Previous ES3 and ES4 development work was awarded to Network Rail Infrastructure Limited under Direct Award Reports RFQ-WMRE-WPG-2025-0001 and MOD-RAIL-WPG-2026-0001. This DAR sets out the award to Network Rail for the next stage of work under ES5. ES5 represents the continuation and further development of the engineering design, surveys, technical assurance and project knowledge established through ES3 and ES4, providing continuity between design stages and avoiding unnecessary duplication or rework. Prototypes and Development This DAR relates to development of upgrades to existing rail stations at Witton and Aston and the work is reliant on NR to develop, assure and integrate the proposed designs with the existing operational railway, including determining compliance with applicable railway standards, asset requirements, safety processes and operational constraints. Network Rail's involvement is therefore integral to progressing the designs to the level of maturity required for subsequent delivery. Single Supplier - intellectual property or other exclusive rights and there are no reasonable alternatives As Network Rail owns the land and railway assets affected by the proposed works, they are best placed to manage the design and enabling solutions required for significant alterations to those assets and to manage the associated engineering, operational and safety risks. The proposed works cannot be developed independently of Network Rail's asset requirements, technical approvals and access arrangements. The owner of the land has a right to determine which supplier can deliver works on that land. Single Supplier - absence of competition for technical reasons and there are no reasonable alternatives As NR own the land and assets, they have the required capability to ensure that any works carried out are interoperable with existing assets, manage interfaces with new or altered infrastructure, manage permits and access to the operational railway and secure any required possessions. Use of an alternative supplier would require these matters to remain subject to Network Rail review, assurance and approval, introducing additional technical and organisational interfaces, with associated programme and delivery risk.

Notice Details

Publication & Lifecycle

Open Contracting ID
ocds-h6vhtk-07b40a
Publication Source
Find A Tender Service
Latest Notice
https://www.find-tender.service.gov.uk/Notice/105286-2026
Current Stage
Award
All Stages
Award

Procurement Classification

Notice Type
UK6 - Contract Award Notice
Procurement Type
Standard
Procurement Category
Works
Procurement Method
Direct
Procurement Method Details
Direct award
Tender Suitability
Not specified
Awardee Scale
Large

Common Procurement Vocabulary (CPV)

CPV Divisions

45 - Construction work

71 - Architectural, construction, engineering and inspection services

79 - Business services: law, marketing, consulting, recruitment, printing and security


CPV Codes

45230000 - Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork

71510000 - Site-investigation services

71520000 - Construction supervision services

71530000 - Construction consultancy services

71540000 - Construction management services

79990000 - Miscellaneous business-related services

Notice Value(s)

Tender Value
Not specified
Lots Value
Not specified
Awards Value
£4,221,520 £1M-£10M
Contracts Value
Not specified

Notice Dates

Publication Date
5 Nov 20261 weeks ago
Submission Deadline
Not specified
Future Notice Date
Not specified
Award Date
30 Oct 20262 weeks ago
Contract Period
17 Nov 2026 - 16 Nov 2027 6-12 months
Recurrence
Not specified

Notice Status

Tender Status
Complete
Lots Status
Complete
Awards Status
Pending
Contracts Status
Not Specified

Buyer & Supplier

Contracting Authority (Buyer)

Main Buyer
West Midlands Combined Authority
Contact Name
Available with D3 Tenders Premium →
Contact Email
Available with D3 Tenders Premium →
Contact Phone
Available with D3 Tenders Premium →

Buyer Location

Locality
BIRMINGHAM
Postcode
B19 3SD
Postcode Area
Birmingham
Country
England

Major Region (ITL 1)
TLG West Midlands (England)
Basic Region (ITL 2)
TLG3 West Midlands
Small Region (ITL 3)
TLG31 Birmingham
Delivery Location
Not specified

Local Authority
Birmingham
Electoral Ward
Newtown
Westminster Constituency
Birmingham Ladywood

Supplier Information

Number of Suppliers
1
Supplier Name

NETWORK RAIL INFRASTRUCTURE LIMITED

Further Information

Notice Documents

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

JSON Markdown