Civil Engineering (Hired Machinery, Maintenance, Crushing and Screening)
Notice Description
The Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery, Maintenance, Crushing and Screening.
Lot Information
Hired Machinery and Maintenance - Tay
The Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - Cowal & Trossachs & Scottish LowlandsThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - West Argyll (South)The Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint
Hired Machinery and Maintenance - LochaberThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - West Argyll (North)The Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - MullThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - GallowayThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - ArranThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Maintenance - Eskdalemuir BypassThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Maintenance.
Renewal: The contract will be for an initial period of 12 months + 12 months + 12 months at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Hired Machinery and Maintenance - West Lochawe Timber Haul RouteThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery and Maintenance.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Crushing Cowal & Trossachs and Scottish LowlandsThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required Crushing and Screening.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Crushing TayThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required Crushing and Screening.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Crushing ArranThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Crushing and Screening.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Crushing Mainland GallowayThe Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Crushing and Screening.
Renewal: The contract will be for an initial period of 2 years with the option of a 2 year extension at the FC's discretion. If the extension is taken, the pricing will be agreed using RPI increase from the end of the two year breakpoint.
Notice Details
Publication & Lifecycle
- Open Contracting ID
- ocds-r6ebe6-0000540706
- Publication Source
- Public Contracts Scotland
- Latest Notice
- https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=FEB344302
- Current Stage
- Award
- All Stages
- Tender, Award
Procurement Classification
- Notice Type
- OJEU - F3 - Contract Award Notice
- Procurement Type
- Standard
- Procurement Category
- Works
- Procurement Method
- Open
- Procurement Method Details
- Open procedure
- Tender Suitability
- Not specified
- Awardee Scale
- SME
Common Procurement Vocabulary (CPV)
- CPV Divisions
43 - Machinery for mining, quarrying, construction equipment
-
- CPV Codes
43310000 - Civil engineering machinery
45200000 - Works for complete or part construction and civil engineering work
45500000 - Hire of construction and civil engineering machinery and equipment with operator
Notice Value(s)
- Tender Value
- £13,078,000 £10M-£100M
- Lots Value
- £13,078,000 £10M-£100M
- Awards Value
- Not specified
- Contracts Value
- £10,718,720 £10M-£100M
Notice Dates
- Publication Date
- 4 Feb 20197 years ago
- Submission Deadline
- 11 Jun 2018Expired
- Future Notice Date
- Not specified
- Award Date
- 19 Nov 20187 years ago
- Contract Period
- Not specified - Not specified
- Recurrence
- Year 2022 for the same requirement.
Notice Status
- Tender Status
- Complete
- Lots Status
- Complete
- Awards Status
- Unsuccessful
- Contracts Status
- Active
Buyer & Supplier
Contracting Authority (Buyer)
- Main Buyer
- Forestry Commission
- Contact Name
- Available with D3 Tenders Premium →
- Contact Email
- Available with D3 Tenders Premium →
- Contact Phone
- Available with D3 Tenders Premium →
Buyer Location
- Locality
- EDINBURGH
- Postcode
- EH12 7AT
- Postcode Area
- Edinburgh
- Country
- Scotland
-
- Major Region (ITL 1)
- TLM Scotland
- Basic Region (ITL 2)
- TLM1 East Central Scotland
- Small Region (ITL 3)
- TLM13 City of Edinburgh
- Delivery Location
- TLM63 Lochaber, Skye and Lochalsh, Arran and Cumbrae, and Argyll and Bute, TLM77 Perth and Kinross, and Stirling, TLM8 West Central Scotland, TLM92 Dumfries and Galloway
-
- Local Authority
- City of Edinburgh
- Electoral Ward
- Corstorphine/Murrayfield
- Westminster Constituency
- Edinburgh West
Further Information
Notice Documents
-
https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=MAY318601
Civil Engineering (Hired Machinery, Maintenance, Crushing and Screening) - The Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery, Maintenance, Crushing and Screening. -
https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=FEB344302
Civil Engineering (Hired Machinery, Maintenance, Crushing and Screening) - The Forestry Commission have a network of forest roads critical to supporting all access which enable the management of the estate. There is a requirement to maintain the existing roads to ensure delivery of the business objectives. Medium Term Contracts (MTC's) are therefore required for Hired Machinery, Maintenance, Crushing and Screening.
Notice URLs
Open Contracting Data Standard (OCDS)
The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.