PKC11964 - A827 Bolfracks Gabion Wall Repair & Scour Protection
Notice Description
The Bolfracks wall is an existing gabion basket retaining wall supporting the A827 between Aberfeldy and Kenmore. The River Tay is at the foot of the wall. The foundations of a 20m long section of wall have been scoured away by the river and have partially collapsed. The works are to remove and replace this failed section of wall and install rockbag scour protection to the full length of the wall. The site has high environmental importance. The A827 road is a key route in the area and road closure duration must be minimised. The works will require the Contractor to; Plan and programme the works to be complete within (or less than) the given road closure duration. Ensure compliance with ecological licence requirements Erect traffic diversion and take full road closure Install rockbag scour protection in River Tay Install temporary works as required Remove existing failed gabions basket wall Rebuild new gabion wall Reconstruct road surface Install new vehicle restraint system The Contractor should note the extensive environmental constraints, licences, and species protection plans. An Ecological Clerk of Works will be employed by the Client to monitor compliance with these requirements.
Lot Information
Lot 1
The Bolfracks wall is an existing gabion basket retaining wall supporting the A827 between Aberfeldy and Kenmore. The River Tay is at the foot of the wall. The foundations of a 20m long section of wall have been scoured away by the river and have partially collapsed. The works are to remove and replace this failed section of wall and install rockbag scour protection to the full length of the wall. The site has high environmental importance. The A827 road is a key route in the area and road closure duration must be minimised. The works will require the Contractor to; Plan and programme the works to be complete within (or less than) the given road closure duration. Ensure compliance with ecological licence requirements Erect traffic diversion and take full road closure Install rockbag scour protection in River Tay Install temporary works as required Remove existing failed gabions basket wall Rebuild new gabion wall Reconstruct road surface Install new vehicle restraint system The Contractor should note the extensive environmental constraints, licences, and species protection plans. An Ecological Clerk of Works will be employed by the Client to monitor compliance with these requirements.. Site visit to take place on Tuesday 2 July 2024. Details can be found on page 9 of Part 1 Bolfracks Instructions for Tenderers document
Notice Details
Publication & Lifecycle
- Open Contracting ID
- ocds-r6ebe6-0000770343
- Publication Source
- Public Contracts Scotland
- Latest Notice
- https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=JUN508188
- Current Stage
- Tender
- All Stages
- Tender
Procurement Classification
- Notice Type
- PCS Notice - Website Contract Notice
- Procurement Type
- Standard
- Procurement Category
- Works
- Procurement Method
- Open
- Procurement Method Details
- Open procedure
- Tender Suitability
- Not specified
- Awardee Scale
- Not specified
Common Procurement Vocabulary (CPV)
- CPV Divisions
45 - Construction work
50 - Repair and maintenance services
-
- CPV Codes
45233140 - Roadworks
45233141 - Road-maintenance works
45233142 - Road-repair works
50230000 - Repair, maintenance and associated services related to roads and other equipment
Notice Value(s)
- Tender Value
- £256,000 £100K-£500K
- Lots Value
- Not specified
- Awards Value
- Not specified
- Contracts Value
- Not specified
Notice Dates
- Publication Date
- 24 Jun 20241 years ago
- Submission Deadline
- 19 Jul 2024Expired
- Future Notice Date
- Not specified
- Award Date
- Not specified
- Contract Period
- Not specified - Not specified
- Recurrence
- Not specified
Notice Status
- Tender Status
- Active
- Lots Status
- Active
- Awards Status
- Not Specified
- Contracts Status
- Not Specified
Buyer & Supplier
Contracting Authority (Buyer)
- Main Buyer
- PERTH & KINROSS COUNCIL
- Contact Name
- Not specified
- Contact Email
- grahamtaylor@pkc.gov.uk
- Contact Phone
- +44 1738475000
Buyer Location
- Locality
- PERTH
- Postcode
- PH1 5PH
- Post Town
- Perth
- Country
- Scotland
-
- Major Region (ITL 1)
- TLM Scotland
- Basic Region (ITL 2)
- TLM0 Eastern Scotland
- Small Region (ITL 3)
- TLM02 Perth and Kinross, and Stirling
- Delivery Location
- TLM77 Perth and Kinross, and Stirling
-
- Local Authority
- Perth and Kinross
- Electoral Ward
- Perth City Centre
- Westminster Constituency
- Perth and Kinross-shire
Further Information
Notice Documents
-
https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=JUN508188
PKC11964 - A827 Bolfracks Gabion Wall Repair & Scour Protection - The Bolfracks wall is an existing gabion basket retaining wall supporting the A827 between Aberfeldy and Kenmore. The River Tay is at the foot of the wall. The foundations of a 20m long section of wall have been scoured away by the river and have partially collapsed. The works are to remove and replace this failed section of wall and install rockbag scour protection to the full length of the wall. The site has high environmental importance. The A827 road is a key route in the area and road closure duration must be minimised. The works will require the Contractor to; Plan and programme the works to be complete within (or less than) the given road closure duration. Ensure compliance with ecological licence requirements Erect traffic diversion and take full road closure Install rockbag scour protection in River Tay Install temporary works as required Remove existing failed gabions basket wall Rebuild new gabion wall Reconstruct road surface Install new vehicle restraint system The Contractor should note the extensive environmental constraints, licences, and species protection plans. An Ecological Clerk of Works will be employed by the Client to monitor compliance with these requirements.
Notice URLs
Open Contracting Data Standard (OCDS)
View full OCDS Record for this contracting process
The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.
{
"tag": [
"compiled"
],
"id": "ocds-r6ebe6-0000770343-2024-06-24T00:00:00Z",
"date": "2024-06-24T00:00:00Z",
"ocid": "ocds-r6ebe6-0000770343",
"initiationType": "tender",
"parties": [
{
"id": "org-26",
"name": "Perth & Kinross Council",
"identifier": {
"legalName": "Perth & Kinross Council"
},
"address": {
"streetAddress": "2 High Street",
"locality": "Perth",
"region": "UKM77",
"postalCode": "PH1 5PH"
},
"contactPoint": {
"email": "Grahamtaylor@pkc.gov.uk",
"telephone": "+44 1738475000",
"url": "http://www.publictendersscotland.publiccontractsscotland.gov.uk"
},
"roles": [
"buyer"
],
"details": {
"classifications": [
{
"id": "Regional or local authority",
"scheme": "TED_CA_TYPE"
},
{
"id": "01",
"description": "General public services",
"scheme": "COFOG"
}
],
"url": "http://www.pkc.gov.uk"
}
},
{
"id": "org-27",
"name": "Perth Sheriff Court",
"identifier": {
"legalName": "Perth Sheriff Court"
},
"address": {
"streetAddress": "County Building, Tay Street",
"locality": "Perth",
"postalCode": "PH2 8NL"
},
"contactPoint": {
"url": "http://"
},
"roles": [
"reviewBody"
]
}
],
"buyer": {
"name": "Perth & Kinross Council",
"id": "org-26"
},
"tender": {
"id": "PKC11964",
"title": "PKC11964 - A827 Bolfracks Gabion Wall Repair & Scour Protection",
"description": "The Bolfracks wall is an existing gabion basket retaining wall supporting the A827 between Aberfeldy and Kenmore. The River Tay is at the foot of the wall. The foundations of a 20m long section of wall have been scoured away by the river and have partially collapsed. The works are to remove and replace this failed section of wall and install rockbag scour protection to the full length of the wall. The site has high environmental importance. The A827 road is a key route in the area and road closure duration must be minimised. The works will require the Contractor to; Plan and programme the works to be complete within (or less than) the given road closure duration. Ensure compliance with ecological licence requirements Erect traffic diversion and take full road closure Install rockbag scour protection in River Tay Install temporary works as required Remove existing failed gabions basket wall Rebuild new gabion wall Reconstruct road surface Install new vehicle restraint system The Contractor should note the extensive environmental constraints, licences, and species protection plans. An Ecological Clerk of Works will be employed by the Client to monitor compliance with these requirements.",
"status": "active",
"items": [
{
"id": "1",
"additionalClassifications": [
{
"id": "50230000",
"scheme": "CPV"
},
{
"id": "45233142",
"scheme": "CPV"
},
{
"id": "45233141",
"scheme": "CPV"
},
{
"id": "45233140",
"scheme": "CPV"
}
],
"deliveryAddresses": [
{
"region": "UKM77"
}
],
"relatedLot": "1"
}
],
"value": {
"amount": 256000,
"currency": "GBP"
},
"procurementMethod": "open",
"procurementMethodDetails": "Open procedure",
"mainProcurementCategory": "works",
"submissionMethod": [
"electronicSubmission"
],
"submissionMethodDetails": "http://www.publictendersscotland.publiccontractsscotland.gov.uk",
"tenderPeriod": {
"endDate": "2024-07-19T12:00:00Z"
},
"awardPeriod": {
"startDate": "2024-07-19T12:00:00Z"
},
"documents": [
{
"id": "JUN508188",
"documentType": "contractNotice",
"title": "PKC11964 - A827 Bolfracks Gabion Wall Repair & Scour Protection",
"description": "The Bolfracks wall is an existing gabion basket retaining wall supporting the A827 between Aberfeldy and Kenmore. The River Tay is at the foot of the wall. The foundations of a 20m long section of wall have been scoured away by the river and have partially collapsed. The works are to remove and replace this failed section of wall and install rockbag scour protection to the full length of the wall. The site has high environmental importance. The A827 road is a key route in the area and road closure duration must be minimised. The works will require the Contractor to; Plan and programme the works to be complete within (or less than) the given road closure duration. Ensure compliance with ecological licence requirements Erect traffic diversion and take full road closure Install rockbag scour protection in River Tay Install temporary works as required Remove existing failed gabions basket wall Rebuild new gabion wall Reconstruct road surface Install new vehicle restraint system The Contractor should note the extensive environmental constraints, licences, and species protection plans. An Ecological Clerk of Works will be employed by the Client to monitor compliance with these requirements.",
"url": "https://www.publiccontractsscotland.gov.uk/search/show/search_view.aspx?ID=JUN508188",
"format": "text/html"
}
],
"lots": [
{
"id": "1",
"description": "The Bolfracks wall is an existing gabion basket retaining wall supporting the A827 between Aberfeldy and Kenmore. The River Tay is at the foot of the wall. The foundations of a 20m long section of wall have been scoured away by the river and have partially collapsed. The works are to remove and replace this failed section of wall and install rockbag scour protection to the full length of the wall. The site has high environmental importance. The A827 road is a key route in the area and road closure duration must be minimised. The works will require the Contractor to; Plan and programme the works to be complete within (or less than) the given road closure duration. Ensure compliance with ecological licence requirements Erect traffic diversion and take full road closure Install rockbag scour protection in River Tay Install temporary works as required Remove existing failed gabions basket wall Rebuild new gabion wall Reconstruct road surface Install new vehicle restraint system The Contractor should note the extensive environmental constraints, licences, and species protection plans. An Ecological Clerk of Works will be employed by the Client to monitor compliance with these requirements.. Site visit to take place on Tuesday 2 July 2024. Details can be found on page 9 of Part 1 Bolfracks Instructions for Tenderers document",
"status": "active",
"hasOptions": false,
"submissionTerms": {
"variantPolicy": "notAllowed"
},
"contractPeriod": {
"durationInDays": 90
},
"hasRenewal": false
}
],
"bidOpening": {
"date": "2024-07-19T12:00:00Z"
},
"contractTerms": {
"hasElectronicPayment": true,
"hasElectronicOrdering": true,
"electronicInvoicingPolicy": "allowed"
},
"coveredBy": [
"GPA"
],
"otherRequirements": {
"requiresStaffNamesAndQualifications": true
},
"selectionCriteria": {
"criteria": [
{
"type": "economic",
"description": "4B.4 The Bidder will be required to state the values for the following for the last two financial years: 1. Current Ratio (Current Assets divided by Current Liabilities) 2. Net Assets (Net Worth) (value per the Balance Sheet) 4B.5.1 The Bidder must confirm they already have, or can commit to obtain, prior to commencement of the contract: Professional Indemnity Insurance Employer's Liability Insurance Public Liability Insurance",
"minimum": "4B.4 Financial Ratios The acceptable range is: 1. Current Ratio - it is expected that the ratio is equal to or greater than 1, i.e. Current Assets will equal or exceed Current Liabilities for both years. Reasons for not meeting the required test to be disclosed by tenderers together with appropriate supporting evidence to confirm the suitability of the tenderer for the contract. 2. Net Assets (Net Worth) - it is expected that the Net Worth will be positive, i.e. a Net Assets position for both years. Reasons for not meeting the required test to be disclosed together with appropriate supporting evidence to confirm the suitability of the tenderer for the contract. 4B.5 Level of Insurance Professional Indemnity Insurance in the sum of GBP2,000,000 for any one occurrence or series of occurrences arising out of one event. Employer's Liability Insurance in the sum of GBP10,000,000 for any one occurrence or series of occurrences arising out of one event. Public Liability Insurance in the sum of GBP5,000,000 for any one occurrence or series of occurrences arising out of one event."
},
{
"type": "technical",
"description": "4C.1 Suppliers will be required to provide six examples of how they have delivered a similar service within the last five years to what is being described. 4C.10 Bidders will be required to confirm whether they intend to subcontract. 4D.1 Quality Management Procedures 4D.1 Health & Safety Procedures",
"minimum": "4C.1 Examples should cover: 2 examples should be projects working under protected species plans or SEPA licences. 2 examples should be projects involving installation of rock bag scour protection. 2 examples should be projects involving construction of gabion basket retaining walls. QU 4D.1 Quality Management Procedures 1. The bidder must hold a UKAS (or equivalent) accredited independent third-party certificate of compliance in accordance with BS EN ISO 9001 (or equivalent), OR 2. The bidder must be able to provide documented evidence of their Quality Management policies and procedures as detailed in the Evaluation Guidance Document. 4D.1 HEALTH AND SAFETY PROCEDURES 1. The bidder must hold a UKAS (or equivalent), accredited independent third-party certificate of compliance in accordance with BS OHSAS 18001 (or equivalent) or have, within the last 12 months, successfully met the assessment requirements of a construction-related scheme in registered membership of the Safety Schemes in Procurement (SSIP) forum. OR, 2. The bidder must be able to provide documented evidence of their Health and Safety policies and procedures as detailed in the Evaluation Guidance Document."
}
]
},
"submissionTerms": {
"languages": [
"en"
],
"bidValidityPeriod": {
"durationInDays": 90
}
},
"classification": {
"id": "45233141",
"scheme": "CPV"
},
"hasRecurrence": false
},
"language": "EN",
"description": "Inspection of the Site: details can be found in document 'Part 1 Bolfracks Instructions for Tenderers', section 14. Please note that the site visit date is Tuesday 2 July 2024. Please advise of attendance via PCS-t messaging portal. The buyer is using PCS-Tender to conduct this ITT exercise. The Project code is 26991. For more information see: http://www.publiccontractsscotland.gov.uk/info/InfoCentre.aspx?ID=2343 Community benefits are included in this requirement. For more information see: https://www.gov.scot/policies/public-sector-procurement/community-benefits-in-procurement/ A summary of the expected community benefits has been provided as follows: Community benefits are included in this requirement, more information on community benefits can be found in the instructions for tenderers document. (SC Ref:770343)",
"links": [
{
"rel": "canonical",
"href": "https://api.publiccontractsscotland.gov.uk/v1/Notice?id=ocds-r6ebe6-0000770343"
}
],
"noticetype": "PCS Notice - Website Contract Notice"
}