This public procurement record has 1 release in its history.

Tender

27 Aug 2026 at 10:40

Summary of the contracting process

Kier Transportation – CP7 NWC is procuring demolition and rail infrastructure works for the redevelopment of Manchester Airport station. The project will provide additional platform capacity to support longer train services and enable two 144-metre trains to operate in two of the station’s four platforms. The works include rail track protection, structural enabling works, demolition of an existing bridge, removal and disposal of road and pavement surfacing, kerbs and ducts, and the careful removal and storage of coping stones and pilaster caps for possible reuse. Further demolition covers parapets, pilasters, precast beams, cill beams, the south abutment and other bridge elements. The work is delivered in a live rail environment at Manchester Airport in the North West.

This procurement has reached the tender stage: the buyer invited suppliers to submit offers through a tender process. The submission deadline is 3 September 2026 at 17:00. The planned contract period runs from 2 February 2027 to 17 April 2028. The estimated value is £100,000, with a minimum estimated value of £50,000, both in GBP. The requirement is classified as works, covering track construction, demolition, site preparation and clearance, and railway-track maintenance. It is suitable for small and medium-sized enterprises. The opportunity concerns a single package of works at Manchester Airport station, including demolition, removal, disposal, storage and rail-protection activities needed for the station capacity scheme.

This opportunity suits demolition and civil engineering contractors with experience of structural demolition, bridge dismantling, site clearance and removal of road, pavement and rail-related materials. Suppliers will need the plant, labour and logistical capacity to dismantle substantial concrete and precast elements, dispose of materials safely, and protect items identified for possible reuse. Rail-sector capability is important because the work involves installing, maintaining and removing track protection and operating within a railway environment. Contractors must be able to plan and work in accordance with relevant rail safety and possession requirements, coordinating activities around railway operations. The requirement is also suited to SMEs able to deliver a focused package of demolition and enabling works within a major station redevelopment.

How relevant is this notice?

Notice Title

Manchester International Airport - Demolition Works

Notice Description

"The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable. Through the project's Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport. The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP): A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services. The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under 'double-stacking' conditions. The scope areas for this package are as follows: -Installation, maintenance and removal of rail track protection. -Structural enabling and demolition works to an existing bridge structure. -Removal and disposal of road and pavement surfacing, kerbs, ducts and associated materials. -Careful removal and storage of existing coping stones and pilaster caps for potential reuse. -Demolition of existing parapets, pilasters, precast beams, cill beams and south abutment concrete. -Demolition and disposal of bridge structural elements in accordance with project requirements. -Working within a rail environment with compliance to all relevant safety and possession requirements."

Publication & Lifecycle

Open Contracting ID
ocds-b5fd17-bf10bb83-a20f-4c2d-82ee-a43249a961da
Publication Source
Contracts Finder
Latest Notice
https://www.contractsfinder.service.gov.uk/Notice/fe55e276-5324-4eb6-b31f-f9922bb3d9d8
Current Stage
Tender
All Stages
Tender

Procurement Classification

Notice Type
Tender Notice
Procurement Type
Standard
Procurement Category
Works
Procurement Method
Not Specified
Procurement Method Details
Tender Suitability
SME
Awardee Scale
Not specified

Common Procurement Vocabulary (CPV)

CPV Divisions

45 - Construction work

50 - Repair and maintenance services


CPV Codes

45111000 - Demolition, site preparation and clearance work

45111100 - Demolition work

45234116 - Track construction works

50225000 - Railway-track maintenance services

Notice Value(s)

Tender Value
£100,000 £100K-£500K
Lots Value
Not specified
Awards Value
Not specified
Contracts Value
Not specified

Notice Dates

Publication Date
27 Aug 20265 days ago
Submission Deadline
3 Sep 20261 day to go
Future Notice Date
Not specified
Award Date
Not specified
Contract Period
2 Feb 2027 - 17 Apr 2028 1-2 years
Recurrence
Not specified

Notice Status

Tender Status
Active
Lots Status
Not Specified
Awards Status
Not Specified
Contracts Status
Not Specified

Contracting Authority (Buyer)

Main Buyer
Kier Transportation - CP7 NWC
Contact Name
Available with D3 Tenders Premium →
Contact Email
Available with D3 Tenders Premium →
Contact Phone
Available with D3 Tenders Premium →

Buyer Location

Locality
CLIPPERS QUAY
Postcode
M50 3XP
Postcode Area
Manchester
Country
England

Major Region (ITL 1)
TLD North West (England)
Basic Region (ITL 2)
TLD3 Greater Manchester
Small Region (ITL 3)
TLD34 Greater Manchester South West
Delivery Location
TLD North West (England)

Local Authority
Salford
Electoral Ward
Quays
Westminster Constituency
Salford

Further Information

Notice Documents

Open Contracting Data Standard (OCDS)

View full OCDS Record for this contracting process

JSON Markdown

The Open Contracting Data Standard (OCDS) is a framework designed to increase transparency and access to public procurement data in the public sector. It is widely used by governments and organisations worldwide to report on procurement processes and contracts.

Loading OCDS record...